CDFM Module 4
What are Joint Acquisition Programs? - ✔✔Joint Acquisition Programs is any acqusition system,
subsystem, component, or technology program with astrategy that includes funding by more than
one DoD compo
...
CDFM Module 4
What are Joint Acquisition Programs? - ✔✔Joint Acquisition Programs is any acqusition system,
subsystem, component, or technology program with astrategy that includes funding by more than
one DoD component during any phase of a system's life cycle.
Who decides to place programs under joint acquisition management? - ✔✔The MDA decides
whether to place programs under joint management and designates the lead executive DoD
component.
What law requires an analysis of potential opportunities of international cooperation? - ✔✔10
USC 2350a(e) requires international cooperation consideration in the initial aquisition strategy
for a program.
When international programs may be established in the defense acqusition program -
✔✔Decision to include international partners needs to be included during development of the
initial capabilities document but no early than the material and solution analysis phase.
When is Earned Value Management (EVM) implemented - ✔✔EVM is part of program
management . It ensures that cost , schedule and technical aspects of the contract are truly
integrated.
In what type of contracts EVM is required - ✔✔EVM is required on Cost, and/or Incentive
contracts valued at greater than $20M.
What is EVM? - ✔✔Earned Value Management is a tool that
1. Relates the scope of the work to its associated budgets and schedule.
2. Measures the work progress in objective terms
3. States that value of the work completed in dollars and other measurable units.
What are EVM techniques? - ✔✔Correlate the budgeted cost of worked scheduled with the
budget cost of work performed (BCWP)
1. 0/100 Earned Value Technique
2. Percent Start/Percent Finish EV Technique (50/50) (25/75) (80/20)
3. Percent Complete
4. Units Completed
5. Equivalent Units
Describe the Percent Start/Percent Finish EV Technique - ✔✔Is an objective earned value
technique tied to the start and completion of a work package task, often referred to % assigned to
the start and finish milestone such as (50/50...)
Thsi technique tends to overstate performance in the first half of the period of performance and
uderstate performance in the last half.
What is the most important step in EVM system? - ✔✔Is the establishment of the Performance
Measurement Baseline (PMB)or the Budgeted Cost of Work Schedule (BCWS)
What is the PMB in and EVM? - ✔✔The PMB includes the undistributed budget, all summary
level planning package budgets, and all control account budgets. It does not include management
reserve.
What is the final step of the PMB? - ✔✔Is to classify work, to allocate the budget and to time
phase the control account work package budgets. This last phase is calculate BWCS
How do we classify work packages in EVM? - ✔✔in 3 categories, Discrete, apportioned effort,
and level of effort.
Describe the realignment of the PMB - ✔✔Rebaselining, Replanning, and Reprogramming
What is Reprogramming? - ✔✔Reprogramming is a comprehensive realignment of the
remaining performance measurement baseline that results in a total budget and/or total schedule
that exceeds the contractual requirements. It is the process that results in an Over-Target
Baseline or OTB and an Over-Target Schedule OTS.
Schedule Performance Index (SPI) formula - ✔✔SPI=BCWP/BCWS
Estimate at Completion (EAC) formula - ✔✔EAC=ACWP+[(BAC-BCWP)/(Performance
Factor)]
EAC Compsite formula - ✔✔ACWPcum+[(BAC-BCWPcum)/(CPIcum*SPIcum)]
Upper Value (worst case)
EVM Terminology - ✔✔EAC=Estimate at Completion
BAC=Budget at Completion(current)
BCWS=Budget Cost of Work Scheduled (current)
BWCP=Budget Cost of Work Performed (earned value)
ACWP=Actual Cost of Work Performed
What is the Contractor Cost and Software Data Reporting (CSDR) - ✔✔The CSDR system
involves two formal contractor reports, the COntractor Cost Data Report (CCDR) and the
Software Resources Data Report (SRDR)
What is Contract Performance Report (CPR) - ✔✔The PM should obtain from the contractor a
CPR (DD form 2734) on all contracts the meet or exceed EVMS dollar thresholds and require
EVMS compliance. The CPR provides contract cost and schedule performance for program
mangement.
What is Contract Funds Status Report (CFSR) - ✔✔(DD 1586) has no specific application
thresholds but PMs should evaluate contracts of less than $1.3M. FFP contracts should not apply
the CFSR unless unusual circumnstances dictate funding visibility.
What is Government Contract Quality Assurance (GCQA) - ✔✔DCMA Q&A personnel
conducts quality assurance as identified in contract administration delegations by the KO.
What is Independent Management Reviews (Peer Reviews) - ✔✔The Director, DPAP organizes
review teams and facilitate pre-award and post-award peer reviews for all service contracts with
a value of $1B or more (including options)
What are Milestone Decision Points? - ✔✔Milestione Decision Points initiate programs and
auhtorize entry into major acquisition process phases
MDP B - ✔✔A favorable decision formally initiates an acquisition program
Where are Technology Readiness Assessments reviewed? - ✔✔At Milestone B & C
Milestone Decision Point C - ✔✔A succesfull outcome at MDP C, results in the program
moving into Production and deployment phase
At what MDP, if necessary, are Independent technology Readiness Assesments done? - ✔✔At
MDP B&C
What are the 4 major reviews? - ✔✔Materiel Development Decision Review
Preliminary Decision Review
Critical Design Review
Full Rate Production Decision Review
What is the role fo USD (AT&L) - ✔✔AT&L is the Defense Acqusition Executive (DAE) and
conducts Defense Acquisition Board reviews for acquisition category ID programs at major
program milestones.
Who advises USD (AT&L) on major acqusitiion decisions?