Which budgeting method below identifies money that should be
added to a project budget to cover cost changes f
...
You passed this Milestone
14 questions were answered correctly.
8 questions were answered incorrectly.
1
Which budgeting method below identifies money that should be
added to a project budget to cover cost changes for a project?
Reserves
Actual
Roll-up
Comparison
CONCEPT
Budget Methods and Evaluation
2
Which of the following elements is NOT included as part of the fivestep process of developing a work breakdown structure?
Identifying deliverables
Sequencing the activities
Developing the budget
Identifying tasks
CONCEPT
Creating a WBS
3
Karen provided advice to the team working on creating a flavored water
beverage since she worked on a similar project in the past.
Karen was assigned which of the following RACI elements?
Consulted
Accountable
Informed
Responsible
CONCEPT
Responsibility Matrix
4
Jani is worried that the team members she assigned to advertise her
company's convention lack the expertise to design creative and informative
brochures.
This would best be categorized as which type of risk?
Resource risk
This study source was downloaded by 100000773243632 from CourseHero.com on 03-30-2022 15:50:32 GMT -05:00
https://www.coursehero.com/file/64476433/BUS-375-Milestone-2docx/
Deliverable risk
Assumption risk
Schedule risk
CONCEPT
Planning Phase Risks
5
Leon started a project to design and create a new video game for the
animation studio where he develops graphics and animations for video
games and movies.
Which item below would be considered an overhead cost?
Animations created for the game
Packaging for the video game
Research time to develop characters and stories
Computers used by staff during the project
CONCEPT
Project Budgeting
6
Which of the following is the least accurate effort estimate?
An effort estimate for a new process
An effort estimate based on past projects
An effort estimate based on assigned resources
An effort estimate based on expertise of individual
CONCEPT
Time and Effort Estimates
7
Which of the following are considered only people project
resources?
Project support staff, software developer, equipment vendor
Project support staff, software developer, machinery
Equipment, project manager, vendors
Project manager, software