Budget Exhibits Module Exam
Here is your test result.The dots represent the choices you have made.
The highlighted questons are the questons you have missed.
Remediaton Accessed shows whether you accessed those links.'N' represents links not visited
and 'Y' represents visited links.
Back to Status page
contains 11 Questons
1) Which of the following informaton is displayed in the P-1 budget exhibit? [Identfy the
purpose, content and conditons requiring submission of the P-1 budget exhibit.]
Line Item Numbers
Narratve justfcaton for each line item`s budget request
Funding requirements for 1 or 2 budget years plus the four years afer to the last budget
year
Informaton on related non-Procurement funding for acquisiton programs
2) Which of the following informaton is displayed in the P-21 budget exhibit? [Identfy the
purpose, content and conditons requiring submission of the P-21 budget exhibit.]
Minimum, economical, and maximum producton rates
Contract history (prior year or last procurement, current year, budget years 1 and 2)
This study source was downloaded by 100000823742721 from CourseHero.com on 07-03-2022 01:03:47 GMT -05:00
https://www.coursehero.com/file/30718088/Budget-Exhibits-Module-Exam-Module-5docx/Contract award informaton for each applicable Work Breakdown Structure element
Listng of all items that will be purchased with advance procurement funds
3) Which one of the following best describes the conditons under which a P-3a budget exhibit is
required to be submited? [Identfy the purpose, content and conditons requiring submission
of the P-3a budget exhibit.]
When it covers a weapon system modifcaton program whose costs exceed $5 million in any
year covered by the budget request
When the advance procurement funding is $5 million or more in any of the budget years
covered by the budget request
When the program element funding is $1 million or more in any budget year covered by the
budget request
When any funding is requested under a partcular Procurement appropriaton
4) Which one of the following best describes the purpose of the P-40a budget exhibit? [Identfy
the purpose, content and conditons requiring submission of the P-40 and P-40a budget
exhibits.]
Provide narratve justfcaton and total procurement costs for each individual end item in an
"items Less Than $5 million" aggregated P-1 line item
Provide budget justfcaton only for a partcular Procurement-funded weapon system
modifcaton program
Provide detailed cost analysis for each R-1 line item (excluding Advance Procurement,
This study source was downloaded by 100000823742721 from CourseHero.com on 07-03-2022 01:03:47 GMT -05:00
https://www.coursehero.com/file/30718088/Budget-Exhibits-Module-Exam-Module-5docx/modifcaton programs, and aggregated line items)
Provide detailed informaton regarding monthly producton of ACAT I program items
5) Which one of the following best describes the purpose of the P-5 budget exhibit? [Identfy the
purpose, content and conditons requiring submission of the P-5 budget exhibit.]
Provide detailed cost analysis for each P-1 line item (excluding Advance Procurement,
modifcaton programs, and aggregated line items)
Provide budget justfcaton for a partcular Procurement-funded weapon system modifcaton
program
Summarize the funding requirements for a partcular Procurement appropriaton account
Provide detailed informaton regarding monthly producton of ACAT I program items
6) Which of the following informaton is displayed in the R-3 budget exhibit? [Identfy the
purpose, content and conditons requiring submission of the R-3 budget exhibit.]
Performing organizaton for each effort requiring over $1 million in funding
Detailed cost informaton for RDT&E projects grouped into 3 categories: Research and
Development, Producton Costs, and Operatons and Support
Funding requirements for 4 out-years following the last budget year
Narratve justfcaton for each program element’s budget request