Oxford Cambridge and RSA Examinations
GCE
Further Mathematics A
Y532/01: Statistics
Advanced Subsidiary GCE
Mark Scheme for November 2020Oxford Cambridge and RSA Examinations
OCR (Oxford Cambridge and RSA) is a lea
...
Oxford Cambridge and RSA Examinations
GCE
Further Mathematics A
Y532/01: Statistics
Advanced Subsidiary GCE
Mark Scheme for November 2020Oxford Cambridge and RSA Examinations
OCR (Oxford Cambridge and RSA) is a leading UK awarding body, providing a wide range of
qualifications to meet the needs of candidates of all ages and abilities. OCR qualifications
include AS/A Levels, Diplomas, GCSEs, Cambridge Nationals, Cambridge Technicals,
Functional Skills, Key Skills, Entry Level qualifications, NVQs and vocational qualifications in
areas such as IT, business, languages, teaching/training, administration and secretarial skills.
It is also responsible for developing new specifications to meet national requirements and the
needs of students and teachers. OCR is a not-for-profit organisation; any surplus made is
invested back into the establishment to help towards the development of qualifications and
support, which keep pace with the changing needs of today’s society.
This mark scheme is published as an aid to teachers and students, to indicate the requirements
of the examination. It shows the basis on which marks were awarded by examiners. It does not
indicate the details of the discussions which took place at an examiners’ meeting before marking
commenced.
All examiners are instructed that alternative correct answers and unexpected approaches in
candidates’ scripts must be given marks that fairly reflect the relevant knowledge and skills
demonstrated.
Mark schemes should be read in conjunction with the published question papers and the report
on the examination.
© OCR 2020Y532/01 Mark Scheme November 2020
2
Text Instructions
1. Annotations and abbreviations
Annotation in RM assessor Meaning
and
BOD Benefit of doubt
FT Follow through
ISW Ignore subsequent working
M0, M1 Method mark awarded 0, 1
A0, A1 Accuracy mark awarded 0, 1
B0, B1 Independent mark awarded 0, 1
SC Special case
^ Omission sign
MR Misread
BP Blank Page
Seen
Highlighting
Other abbreviations in
mark scheme
Meaning
dep* Mark dependent on a previous mark, indicated by *. The * may be omitted if only one previous M mark
cao Correct answer only
oe Or equivalent
rot Rounded or truncated
soi Seen or implied
www Without wrong working
AG Answer given
awrt Anything which rounds to
BC By Calculator
DR This question included the instruction: In this question you must show detailed reasoning.Y532/01 Mark Scheme November 2020
3
2. Subject-specific Marking Instructions for A Level Mathematics A
a Annotations must be used during your marking. For a response awarded zero (or full) marks a single appropriate annotation (cross, tick, M0 or ^) is
sufficient, but not required.
For responses that are not awarded either 0 or full marks, you must make it clear how you have arrived at the mark you have awarded and all responses
must have enough annotation for a reviewer to decide if the mark awarded is correct without having to mark it independently.
It is vital that you annotate standardisation scripts fully to show how the marks have been awarded.
Award NR (No Response)
- if there is nothing written at all in the answer space and no attempt elsewhere in the script
- OR if there is a comment which does not in any way relate to the question (e.g. ‘can’t do’, ‘don’t know’)
- OR if there is a mark (e.g. a dash, a question mark, a picture) which isn’t an attempt at the question.
Note: Award 0 marks only for an attempt that earns no credit (including copying out the question).
If a candidate uses the answer space for one question to answer another, for example using the space for 8(b) to answer 8(a), then give benefit of doubt
unless it is ambiguous for which part it is intended.
b An element of professional judgement is required in the marking of any written paper. Remember that the mark scheme is designed to assist in marking
incorrect solutions. Correct solutions leading to correct answers are awarded full marks but work must not always be judged on the answer alone, and
answers that are given in the question, especially, must be validly obtained; key steps in the working must always be looked at and anything unfamiliar
must be investigated thoroughly. Correct but unfamiliar or unexpected methods are often signalled by a correct result following an apparently incorrect
method. Such work must be carefully assessed. When a candidate adopts a method which does not correspond to the mark scheme, escalate the
question to your Team Leader who will decide on a course of action with the Principal Examiner.
If you are in any doubt whatsoever you should contact your Team Leader.Y532/01 Mark Scheme November 2020
4
c The following types of marks are available.
M
A suitable method has been selected and applied in a manner which shows that the method is essentially understood. Method marks are not usually lost
for numerical errors, algebraic slips or errors in units. However, it is not usually sufficient for a candidate just to indicate an intention of using some method
or just to quote a formula; the formula or idea must be applied to the specific problem in hand, e.g. by substituting the relevant quantities into the formula.
In some cases the nature of the errors allowed for the award of an M mark may be specified.
A method mark may usually be implied by a correct answer unless the question includes the DR statement, the command words “Determine” or “Show
that”, or some other indication that the method must be given explicitly.
A
Accuracy mark, awarded for a correct answer or intermediate step correctly obtained. Accuracy marks cannot be given unless the associated Method mark
is earned (or implied). Therefore M0 A1 cannot ever be awarded.
B
Mark for a correct result or statement independent of Method marks.
Unless otherwise indicated, marks once gained cannot subsequently be lost, e.g. wrong working following a correct form of answer is ignored. Sometimes
this is reinforced in the mark scheme by the abbreviation isw. However, this would not apply to a case where a candidate passes through the correct
answer as part of a wrong argument.
d When a part of a question has two or more ‘method’ steps, the M marks are in principle independent unless the scheme specifically says otherwise; and
similarly where there are several B marks allocated. (The notation ‘dep*’ is used to indicate that a particular mark is dependent on an earlier, asterisked,
mark in the scheme.) Of course, in practice it may happen that when a candidate has once gone wrong in a part of a question, the work from there on is
worthless so that no more marks can sensibly be given. On the other hand, when two or more steps are successfully run together by the candidate, the
earlier marks are implied and full credit must be given.
e The abbreviation FT implies that the A or B mark indicated is allowed for work correctly following on from previously incorrect results. Otherwise, A and B
marks are given for correct work only – differences in notation are of course permitted. A (accuracy) marks are not given for answers obtained from
incorrect working. When A or B marks are awarded for work at an intermediate stage of a solution, there may be various alternatives that are equally
acceptable. In such cases, what is acceptable will be detailed in the mark scheme. If this is not the case please, escalate the question to your Team
Leader who will decide on a course of action with the Principal Examiner.
Sometimes the answer to one part of a question is used in a later part of the same question. In this case, A marks will often be ‘follow through’. In such
cases you must ensure that you refer back to the answer of the previous part question even if this is not shown within the image zone. You may find it
easier to mark follow through questions candidate-by-candidate rather than question-by-question.
f We are usually quite flexible about the accuracy to which the final answer is expressed; over-specification is usually only penalised where the scheme
explicitly says so.
• When a value is given in the paper only accept an answer correct to at least as many significant figures as the given value.Y532/01 Mark Scheme November 2020
5
• When a value is not given in the paper accept any answer that agrees with the correct value to 3 s.f. unless a different level of accuracy has been
asked for in the question, or the mark scheme specifies an acceptable range.
NB for Specification B (MEI) the rubric is not specific about the level of accuracy required, so this statement reads “2 s.f”.
Follow through should be used so that only one mark in any question is lost for each distinct accuracy error.
Candidates using a value of 9.80, 9.81 or 10 for g should usually be penalised for any final accuracy marks which do not agree to the value found with 9.8
which is given in the rubric.
g Rules for replaced work and multiple attempts:
• If one attempt is clearly indicated as the one to mark, or only one is left uncrossed out, then mark that attempt and ignore the others.
• If more than one attempt is left not crossed out, then mark the last attempt unless it only repeats part of the first attempt or is substantially less
complete.
• if a candidate crosses out all of their attempts, the assessor should attempt to mark the crossed out answer(s) as above and award marks
appropriately.
h For a genuine misreading (of numbers or symbols) which is such that the object and the difficulty of the question remain unaltered, mark according to the
scheme but following through from the candidate’s data. A penalty is then applied; 1 mark is generally appropriate, though this may differ for some units.
This is achieved by withholding one A or B mark in the question. Marks designated as cao may be awarded as long as there are no other errors.
If a candidate corrects the misread in a later part, do not continue to follow through. Note that a miscopy of the candidate’s own working is not a misread
but an accuracy error.
i If a calculator is used, some answers may be obtained with little or no working visible. Allow full marks for correct answers, provided that there is nothing in
the wording of the question specifying that analytical methods are required such as the bold “In this question you must show detailed reasoning”, or the
command words “Show” or “Determine”. Where an answer is wrong but there is some evidence of method, allow appropriate method marks. Wrong
answers with no supporting method score zero. If in doubt, consult your Team Leader.
j If in any case the scheme operates with considerable unfairness consult your Team Leader.Y532/01 Mark Scheme November 2020
6
Question Solution Marks AOs Guidance
1 (a) –0.954 BC B2
[2]
1.1
1.1
SC: If B0, give B1 if two of 7.04, 29.0[4], –13.6[4]
(or 35.2, 145[.2], –68.2) seen
(b) Points lie close to a straight line
Line has negative gradient
B1
B1
[2]
2.2b
1.1
Must refer to line, not just “negative correlation”
(c) No, it will be the same as x → a is a
linear transformation
B1
[1]
2.2a OE. Either “same” with correct reason, or “disagree” with correct
reason. Allow any clear valid technical term
2 (a) 1
5
0.2
=
M1
A1
[2]
3.3
1.1
Geometric distribution soi
5 (or 5.00…) only
(b) 0.82 – 0.810
= 0.533 (0.5326258…)
M1
A1
[2]
1.1
3.4
Allow for powers 2, 3, 4 and 9, 10, 11.
Awrt 0.533, www.
[5201424/9765625]
0.506, 0.378, 0.275, 0.405,
0.302, 0.554, 0.426, 0.324
Or 0.2(0.82 + …. + 0.89),
± 1 term at either end
(c) P(≥ 10) = 0.89
= 0.1342…
B(30, 0.1342…)
Variance = npq = 3.486…
M1
A1
M1
A1ft
[4]
3.1b
1.1
3.1b
1.1
Or 0.810. Can be implied by correct p
[0.10737… is M1A0 here]
Stated or implied, their 0.89 or 0.810
In range [3.48, 3.49]
2.875 from 0.810: M1A0M1A1ft
SC: 0.134(2) oe not
properly shown: B2 for
correct final answer.Y532/01 Mark Scheme November 2020
7
Question Solution Marks AOs Guidance
3 (a) Neither B1
[1]
1.2
(b) q = 1.13 + 0.620p B1B1
B1
[3]
1.1,1.1
1.1
0.62(0) correct; both numbers correct
Fully correct answer including letters
(c) (i) 2.68 B1ft
[1]
1.1 awrt 2.68, ft on their (b) if letters correct
(c) (ii) 2.5 is within data range, and points
(here) are close to line/well correlated
B1
B1
[2]
2.2b
2.2b
At least one reason, allow “no because points not close to line”
Full argument, two reasons needed
(d) Not much data here/points scattered/
possible outliers
So not very reliable
M1
A1
[2]
2.3
1.1
Reason for not very reliable (not “extrapolation”)
Full argument and conclusion, not too assertive (not wholly
unreliable!)
4 (a) Test is for rankings/rankings
arbitrary/not bivariate normal etc
B1
[1]
2.4 OE
(b) H0: ρs = 0, H1: ρs > 0, where ρs is the
population rank correlation coefficient
B1 1.1 Allow ρs not defined; allow ρ.
Allow: H0: no association between rankings.
Ranks 5 4 3 6 1 2
5 1 2 6 4 3
Σd 2 = 20 B1 1.1
H1: positive association (but not H1: association)
6 20
1
s 6 35
r
×
= −
×
M1 1.1
= 3/7 or 0.42857… A1 1.1 Exact or awrt 0.429
< 0.9429 B1 1.1
Do not reject H0 M1ft 1.1 FT on their Σd 2 only
Insufficient evidence of association
between ranking given by the two
categories
A1ft
[7]
2.2b
(c) Not dependent on any distributional
assumptions
B1
[1]
1.2 Oe (cf. Specification, 5.08f)Y532/01 Mark Scheme November 2020
8
Question Solution Marks AOs Guidance
5 (a) Expected frequency for Middle/25 to 60
is 4.4
which is < 5 so must combine cells
B1*ft
depB1
[2]
2.4
3.5b
Correctly obtain this FE, ft on addition errors
“< 5” explicit and correct deduction
(b) Early Middle Late
29.4 23.1 31.5
26.6 20.9 28.5
B1 1.1 Both, allow 28.4 for 28.5
awrt 2.29, but allow 2.3
In range [2.53, 2.54]
Early Middle Late
0.9918 0.4160 2.2937
1.0962 0.4598 2.5351
B1
B1
[3]
1.1
1.1
(c) H0: no association between session and
age group. H1: some association
ΣX 2 = 7.793
ν = 2, χ2(2)crit = 5.991
Reject H0.
Significant evidence of association
between session attended and age
group.
B1
B1
B1
M1ft
A1ft
[5]
1.1
1.1
1.1
1.1
2.2b
Both. Allow “independent” etc
Correct value of X 2, awrt 7.79 (allow even if wrong in (b))
Correct CV and comparison
Correct first conclusion, FT on their TS only
Contextualised, not too assertive
(d) The two biggest contributions to χ2 are
both for the late session …
… when the proportion of younger
people is higher, and of older people is
lower, than the null hypothesis would
suggest.
M1ft
A1ft
[2]
1.1
2.4
Refer to biggest contribution(s), FT on their answers to (b), needs
“reject H0”
Full answer, referring to at least one cell (ignore comments on next
highest cells)Y532/01 Mark Scheme November 2020
9
Question Solution Marks AOs Guidance
6 (a) Failures occur to no fixed pattern/are
not predictable
B1
[1]
1.1 OE. NOT “independent”
(b) Failures occur independently of one
another
and at constant average rate
B1
B1
[2]
1.1
1.1
Not recoverable from (a) if independence not restated here; must
be contextualised
Ignore “singly”. Allow “uniform” rate, not “constant rate” or
“constant probability”; must be contextualised
(c) Variance (1.6384) ≈ mean
So suggests that it is likely to be well
modelled
M1
A1
[2]
1.1
3.5a
Compare variance (or SD). Allow square/square-root confusion
Correct comparison and conclusion, 1.64 or better seen
(d) e−1.61 B1
[1]
3.4 Exact needed, allow even if 0! or 1.610 or both left in
(e) 1 ≥ 2
0.322 0.478
B1
B1
[2]
3.4
1.1
One correct e.g. 0.3218
Other correct e.g. 0.4783
(f) P(F = 1) will be smaller as single
failures are less likely
B1*
depB1
[2]
3.5c
3.3 OE. Partial answer: B1Y532/01 Mark Scheme November 2020
10
Question Solution Marks AOs Guidance
7 2
2
3
3
2 (2 1) 3 (3 1)(3 2)
2 6
m
m
C m
C
m m m m m
m
×
− − −
= × ÷
M1
M1
3.1b
3.1b
Use 2mC2 and m
Divide by 3mC3
=
2 (2 1)
(3 1)(3 2)
m m
m m
−
− −
A1 2.1 Correct expression in terms of m
(allow with m not cancelled yet)
28
55
2 (2 1)
(3 1)(3 2)
m m
m m
−
=
− −
M1 3.1a Equate to 55 28 & simplify to three-term quadratic
⇒ 16m2 – 71m + 28 = 0 A1 2.1 Correct simplified quadratic, or (quadratic) × m, = 0, aef
m = 4 BC M1 1.1 Solve to get both 4 and 16 7
Reject m = 16 7 as m is an integer A1
[7]
3.2a Explicitly reject m = 16 7
OR: 2 (2 1) 3!
3 (3 1)(3 2) 2
m m m
m m m
− × ×
− − ×
then as above
Multiplication method can get full marks, but if no 3 or 3!, max
M1M0A0 M1A0M0A0OCR (Oxford Cambridge and RSA Examinations)
The Triangle Building
Shaftesbury Road
Cambridge
CB2 8EA
OCR Customer Contact Centre