Contract Management Exam
Here is your test result.The dots represent the choices you have made.
The highlighted questions are the questions you have missed.
Remediation Accessed shows whether you accessed those links.
...
Contract Management Exam
Here is your test result.The dots represent the choices you have made.
The highlighted questions are the questions you have missed.
Remediation Accessed shows whether you accessed those links.'N' represents links not visited and 'Y'
represents visited links.
Back to Status page
contains 9 Questions
1) The COR should be familiar with all the following areas of a contract: [Recognize the basic
information (period of performance, PWS, contract value) found in a contract to include the uniform
contract format]
All these statements are correct
The Period of Performance
The Statement of Work or Performance Work Statement
The contract value
2) Accounting data is entered at the CLIN level with ACRNS as shorthand for tracking LOAs.
[Identify methods of tracking contract obligations using ACRNS and CLINs in a contract]
True
False
3) What areas of the contract under the Uniform Contract Format specify schedule/delivery
parameters for the COR? [Analyze contract schedule compliance, to include all SOW requirements and
CDRL deliverables]
All the answers are correct
Section B – Supplies or Services and Prices/Costs
Section C - Description/Specifications/Statement of Work
Section F – Deliverables or Performance
4) A bilateral modification is used to_____________. [Identify COR responsibilities supporting the
planning and submission of contract changes documents needed to negotiate a modification]
All of these answers are correct
Make a change in the contract both parties agree with
Make negotiated equitable adjustment to a change order
Definitize a letter contract
DAU Page 1 of 2
https://learn.dau.mil/Atlas2/html/testengine/TestGeneration/test_review.jsp 11/17/20185) An option is the unilateral right of the government to extend or buy more than the amounts
bought at the time of award. [Determine if a change is within the scope of the contract.]
True
False
6) Contracting Officer's Representatives do not have authority to modify the contract; however,
they are vital to the process as they are relied upon to notify the Contracting Officer of required
contract changes and evaluating proposals. [Define the COR's role in the resolution of issues under
the contract and his role in monitoring corrective actions]
True
False
7) During negotiations for a proposed change to the contract, the COR may be asked to:
[Recognize how the COR's responsibility for providing cost estimates assist KOs in negotiating proposed
changes in scope of work under the contract.]
Evaluate proposed travel to include location and number of trips.
Evaluate the technical approach.
All these responses are correct
Evaluate the proposed hours and labor categories.
8) The Contracting Officer's Representative needs to be careful when giving technical direction to
the contractor that they do not provide Improper Technical Direction which includes which of the
following? [Identify the common causes of constructive change]
Failure to take action in the face of late or poor performance
Requiring the contractor to perform in accordance with contract specifications
Allowing the contractor to substitute a method of performance when there is no contractual
prohibition against it
Preventing one contractor from interfering with another
9) An unauthorized commitment is caused by government personnel obligating the government
without contract authority. [Identify the duty to provide technical clarification to the Contractor without
creating an unauthorized obligation or constructive change to the contract]