What are some of the extension item types can be transported from the Quality system to the Production System
Form Templates
Custom Fields
Query Designer Report
What are some of the defined recommendations for organi
...
What are some of the extension item types can be transported from the Quality system to the Production System
Form Templates
Custom Fields
Query Designer Report
What are some of the defined recommendations for organizational change success?
Maintain a robust governance structure, especially in the run phase
Promote the case for change and look forward to avoid change fatigue
Be aware of the cultural and language barriers for regions, countries, and Lines of Business impacted.
Which of the following SAP S/4HANA Landscape Transformation options are enabled
Migration of selected applications
Migration of business unit
System Consolidation
Which of the following project phases is it important to plan and schedule data loads followed by load validation activites
Explore
Which of the following are key responsibilities of the Scrum Master
Team Protection
Team Support
Leadership Skill
What is the purpose of the Solution Builder tool in the SAP Activate Guided Configuration
To activate the Best Practice content
Which activities are part of the Design and Configuration application of the SAP Activate Methodology
225-769-3600
Dr. Casadaban
Dr. Regean
Dr. Nelson
Perform Fit/Gap Analysis
Conduct Scope Validation
Which of the following is true about a cloud implementation project?
The Starter System is specific to S/4 HANA Cloud
In the prepare phase of a cloud implementation project the project team provide the customer with materials to review as self-enablement.
SAP now offers the ability to deploy and manage solutions in which of the following environments.
Cloud, On-Premise and Hybrid
Which of the following are available in the initial SAP methodologies JAM page
Roadmaps
Accelerators
In the System conversion to SAP S/4 HANA Deploy phase, which of the following tasks are included
Final testing
Which of the following statements about Scrum is correct
The three ceremonies are sprint planning, daily scrum, sprint (retrospective).
In which SAP Activate methodology phase does the team identify and design functional quick wins scope of the conversion project
Explore
How can the project manager help to keep momentum in the project and help to keep the customer involved
Leverage agile cycles to build and test the solution
Add customer resources to the project to reduce the need for formal training.
What structure level do you see when you access the Roadmap Viewer and chose work stream navigation
Deliverable
Which of following can be used to navigate through the roadmap
Workstreams