Cost Variance formula - ANSWER Earned Value (EV) - Actual Cost (AC)
What are the 6 constraints? - ANSWER Scope, Risk, Resources, Quality, Schedule, Budget
Initiating (Process Group) - ANSWER Processes performed to
...
Cost Variance formula - ANSWER Earned Value (EV) - Actual Cost (AC)
What are the 6 constraints? - ANSWER Scope, Risk, Resources, Quality, Schedule, Budget
Initiating (Process Group) - ANSWER Processes performed to define a new PROJECT or a new PHASE of an existing project
Planning (Process Group) - ANSWER Processes performed to establish total scope of effort, define and refine objectives, and develop a course of action to attain the objectives
Executing (Process Group) - ANSWER Processes performed to complete the work defined in the project management plan to satisfy objectives
Monitoring & Controlling (Process Group) - ANSWER Processes to track, review, and orchestrate progress and performance of a project
How many processes are in EXECUTING? - ANSWER 8
How many processes are in PLANNING? - ANSWER 24
How many processes are in INITIATING? - ANSWER 2
How many processes are in CLOSING? - ANSWER 2
How many processes are in MONITORING & CONTROLLING? - ANSWER 11
What are INPUTS? - ANSWER Tools and Techniques you can use to DO the process
What are OUTPUTS? - ANSWER One or more things you can GET as a RESULT of doing the process
How many processes are there? - ANSWER 47
How many knowledge areas are there? - ANSWER 10
What are the 10 knowledge areas? - ANSWER Integration, Scope, Time, Cost, Quality, Human Resources, Communication, Risk, Procurement, Stakeholder
Closing (Process Group) - ANSWER Processes to conclude all activities across all process groups of a project
Validate Scope: What process group? What knowledge area? - ANSWER Monitoring & Controlling (PG)
Scope Management (KA)
Validate Scope: What Tools and Techniques? - ANSWER Inspection
Group Decision Making
Develop Project Charter: What process group? What knowledge area? - ANSWER Initiating (PG)
Integration Management (KA)
Develop Project Charter: What Tools and Techniques? - ANSWER Expert Judgement
Facilitation Techniques
Create WBS: What process group? What knowledge area? - ANSWER Planning (PG)
Scope Management (KA)
Create WBS: What Tools and Techniques? - ANSWER Decomposition
Expert Judgement
Plan Scope Management: What process group? What knowledge area? - ANSWER Planning (PG)
Scope Management (KA)
Plan Scope Management: What Tools and Techniques? - ANSWER Expert Judgement
Meetings
Direct & Manage Project Work: What process group? What knowledge area? - ANSWER Executing (PG)
Integration Management (KA)
Direct & Manage Project Work: What Tools and Techniques? - ANSWER Expert Judgement
PMIS
Meetings
Monitor & Control Project Work: What process group? What knowledge area? - ANSWER Monitoring and Controlling (PG)
Integration Management (KA)
Monitor & Control Project Work: What Tools and Techniques? - ANSWER Expert Judgement
Analytical Techniques
PMIS
Meetings
Perform Integrated Change Control: What process group? What knowledge area? - ANSWER Monitoring and Controlling (PG)
Integration Management (KA)
Perform Integrated Change Control: What Tools and Techniques? - ANSWER Expert Judgement
Meetings
Change Control Tools
Close Project or Phase: What process group? What knowledge area? - ANSWER Closing (PG)
Integration Management (KA)
Close Project or Phase: What Tools and Techniques? - ANSWER Expert Judgement
Analytical Techniques
Meetings
Define Scope: What process group? What knowledge area? - ANSWER Planning (PG)
Scope Management (KA)
Define Scope: What Tools and Techniques? - ANSWER Expert Judgement
Product Analysis
Alternatives Generation
Facilitated Workshops
Collect Requirements: What process group? What knowledge area? - ANSWER Planning (PG)
Scope Management (KA)
Collect Requirements: What Tools and Techniques? - ANSWER Interviews
Focus Groups
Facilitated Workshops
Group Creativity Techniques
Group Decision Making
Questionnaires and Surveys
Observations
Prototypes
Benchmarking
Context Diagrams
Document Analysis
Control Scope: What process group? What knowledge area? - ANSWER Monitoring & Controlling (PG)
Scope Management (KA)
Control Scope: What is the ONLY Tool/Technique? - ANSWER Variance Analysis
Develop Project Management Plan: What process group? What knowledge area? - ANSWER Planning (PG)
Integration Management (KA)
Develop Project Management Plan: What Tools and Techniques? - ANSWER Expert Judgement
Facilitation Techniques
What is a Requirements Management Plan? - ANSWER Plan that says HOW requirements will be analyzed, documented and recorded.
This is PART OF the Project Management Plan
Does NOT say what is in and out of scope
What is Variance Analysis? - ANSWER A technique for determining CAUSE and DEGREE of difference between baseline and performance.
What is TOTAL FLOAT? - ANSWER Amount of time an activity can be delayed without delaying the completion date
What is the formula for TOTAL FLOAT? - ANSWER Late Start (LS) - Early Start (ES)
OR
Late Finish (LF) - Early Finish (EF)
Plan Schedule Management: What process group? What knowledge area? - ANSWER Planning (PG)
Time Management (KA)
Plan Schedule Management: What Tools and Techniques? - ANSWER Expert Judgement
Analytical Techniques
Meetings
Define Activities: What process group? What knowledge area? - ANSWER Planning (PG)
Time Management (KA)
Define Activities: What Tools and Techniques? - ANSWER Decomposition
Rolling wave planning
Expert Judgement
Sequence Activities: What process group? What knowledge area? - ANSWER Planning (PG)
Time Management (KA)
Sequence Activities: What Tools and Techniques? - ANSWER Precedence Diagramming method (PDM)
Dependency Determination
Leads and Lags
Estimate Activity Duration: What process group? What knowledge area? - ANSWER Planning (PG)
Time Management (KA)
Estimate Activity Duration: What Tools and Techniques? - ANSWER Expert Judgement
Analogous estimating
Parametric estimating
Three-point estimating
Group Decision making techniques
Reserve analysis
Develop Schedule: What process group? What knowledge area? - ANSWER Planning (PG)
Time Management (KA)
Develop Schedule: What Tools and Techniques? - ANSWER Schedule Network Analysis
Critical Path method
Critical Chain method
Resource Optimization techniques
Modeling techniqies
Leads and Lags
Schedule Compression
Scheduling tool
Control Schedule: What process group? What knowledge area? - ANSWER Monitoring and Controlling (PG)
Time Management (KA)
Control Schedule: What Tools and Techniques? - ANSWER Performance Reviews
PMIS
Resource Optimization techniques
Modeling techniqies
Leads and Lags
Schedule Compression
Scheduling tool
Estimate Activity Resources: What process group? What knowledge area? - ANSWER Planning (PG)
Time Management (KA)
Estimate Activity Resources: What Tools and Techniques? - ANSWER Expert Judgement
Alternative Analysis
Published estimating data
Bottom Up Estimating
PMIS
Plan Cost Management: What process group? What knowledge area? - ANSWER Planning (PG)
Cost Management (KA)
Plan Cost Management: What Tools and Techniques? - ANSWER Expert Judgement
Analytical Techniques
Meetings
Estimate Costs: What process group? What knowledge area? - ANSWER Planning (PG)
Cost Management (KA)
Estimate Costs: What Tools and Techniques? - ANSWER Expert Judgement
Analogous estimating
Parametric estimating
Bottom up estimating
Three-point estimating
Reserve analysis
Cost of quality
PMIS
Vendor Bid analysis
Group Decision making techniques