Number of Communication Channels - ANSWER n(n-1)/2
Schedule Performance Index - ANSWER SPI = EV/PV
Cost Performance Index - ANSWER CPI = EV/AC
Schedule Variance - ANSWER SV = EV-PV
Cost Variance - ANSWER CV =
...
Number of Communication Channels - ANSWER n(n-1)/2
Schedule Performance Index - ANSWER SPI = EV/PV
Cost Performance Index - ANSWER CPI = EV/AC
Schedule Variance - ANSWER SV = EV-PV
Cost Variance - ANSWER CV = EV - AC
Estimate at Completion if original was flawed - ANSWER EAC = AC + New ETC
Estimate at Completion if current cost is accepted and future costs will be as budgeted - ANSWER EAC = AC + (BAC - EV)
Estimate at Completion if what has been happening is expected to continue - ANSWER EAC = BAC/CPI
Estimate at Completion if CPI and SPI are considered - ANSWER EAC = AC + (BAC - EV)/ (CPI*SPI)
To-Complete Performance Index based on budget at completion - ANSWER TCPI = (BAC-EV)/(BAC - AC)
To-Complete Performance Index based on Estimate at completion - ANSWER TCPI = (BAC-EV)/(EAC-AC)
Estimate to Completion - ANSWER ETC = EAC - AC
Variance at Completion - ANSWER VAC = BAC - EAC
PERT Estimation: Beta - ANSWER (O+4M+P)/6
PERT Estimation: Triangular - ANSWER (O+P+M)/3
Standard Deviation - ANSWER (P-O)/6
Variance - ANSWER [(P-O)/6]^2
1 sigma - ANSWER 68.28%
2 Sigma - ANSWER 95.46%
3 Sigma - ANSWER 99.73%
6 Sigma - ANSWER 99.999%
Total Float - ANSWER LS - ES or LF - EF
Expected Monetary Value - ANSWER EMV = Probability of Outcome * Value of Outcome
Decision Tree Analysis Steps - ANSWER 1. Investment + Impact
2. Revised Impact * Probability
3. Add all EMV
W. Edwards Deming - ANSWER Known as the father of modern quality
14 Steps to Quality Management
Plan Do Check Act Cycle (Deming or Shewart Cycle)
Improved production in US during WWII
Taught senior management in Japan about quality
Joseph Juran - ANSWER Connected to Pareto Principle
Believed that results should be "fit for use" by the customer
Believed in getting management involved
Pareto Principle - ANSWER Also known as 80/20 Rule or principle
80% of defects are a result of 20% of causes
Named after Vildfredo Pareto
Added "people aspect" into Quality Management
Phil Crosby - ANSWER Zero Defect
Cost of Poor Quality
The idea that quality is "conformance to requirements"
14 Steps of Quality Improvement
Defect prevention is preferred
The price of non-conformance is measured in monetary terms
Abraham Maslow - ANSWER Maslow's Hiearchy of Needs
Self Actualization
Esteem
Love
Safety
Basic Physiological Needs
Douglas McGregor - ANSWER McGregor's Theory of X and Y
Theory X - Believes employees must be managed closely; authoritative, quick to blame employees
Theory Y - Believes employees are self-motivated; provides space for employees to motivate themselves
Fredrick Herzberg - ANSWER Herzberg's Motivation/ Hygiene Theory
Factors that affect people's attitude at work
Hygiene: Required but does not result in job satisfaction; work conditions, salary, safety, supervision, job security
Motivators: Results in job satisfaction when hygiene factors are also met; recognition, responsibility, work challenges.
David McClelland - ANSWER Achievement Theory
People are motivated by the need for achievement, power, and affiliation
Victor Vroom - ANSWER Expectancy Theory
Employees will place more effort into better performance if it leads to rewards valued by them
Bruce Tuckman - ANSWER Stages of Team Development
1. Forming
2. Storming
3. Norming
4. Performing
5. Adjourning
Develop Project Charter Outputs - ANSWER Project Charter
Develop Project Management Plan Outputs - ANSWER Project Management Plan
Direct and Manage Project Work Outputs - ANSWER Deliverables
Work performance data
Change requests
PM Plan Updates
Project Documents Updates
Monitor and Control Project Work Outputs - ANSWER Change requests
Work performance reports
PM Plan updates
Project documents updates
Perform Integrated Change Control Outputs - ANSWER Approved Change requests
Change Log
PM Plan updates
Project Documents Updates
Close Project or Phase Outputs - ANSWER Final Product, service or result transition
Organizational process assets updates
Plan Scope Management Outputs - ANSWER Scope Management Plan
Requirements management plan
Collect Requirements Outputs - ANSWER Requirements documentation
Requirements traceability matrix
Define Scope Outputs - ANSWER Project Scope statement
Project doc updates
Create WBS Outputs - ANSWER Scope Baseline
Project doc updates
Validate Scope Outputs - ANSWER Accepted Deliverables
Change Requests
Work performance information
Project doc updates
Control Scope Outputs - ANSWER Work Performance Information
Change requests
Project Management plan updates
Project Documents updates
Organizational process assets updates
Plan Schedule Management Outputs - ANSWER Schedule management plan
Define Activities Outputs - ANSWER Activity list
Activity attributes
Milestone list
Sequence Activities Outputs - ANSWER Project Schedule Network diagrams
Project doc updates
Estimate Activity Resources Outputs - ANSWER Activity resource requirements
Resource breakdown structure
Project documents updates
Estimate Activity Durations Outputs - ANSWER Activity Duration Estimates
Project doc updates
Develop Schedule Outputs - ANSWER Schedule baseline
Project Schedule
Schedule data
Project calendars
PM Plan updates
Project doc updates
Control Schedule Outputs - ANSWER Work performance information
Schedule forecasts
Change requests
PM Plan updates
Project doc updates
Organizational process assets updates
Plan Cost Management Outputs - ANSWER Cost Management Plan
Estimate Costs Outputs - ANSWER Activity cost estimates
Basis of estimates
Project doc updates
Determine Budget Outputs - ANSWER Cost baseline
Project funding requirements
Project documents updates
Control Costs Outputs - ANSWER Work performance information
Cost forecasts
Change requests
PM Plan updates
Project doc updates
Organizational Process Assets updates
Plan Quality Management Outputs - ANSWER Quality Management Plan
Process Improvement plan
Quality Metrics
Quality checklist
Project doc updates
Perform Quality Assurance Outputs - ANSWER Change requests
PM Plan updates
Project doc updates
Organizational process assets updates
Control Quality Outputs - ANSWER Quality Control measurements
Validated changes
Verified deliverables
Work performance information
Change requests
PM Plan updates
Project doc updates
Organizational process assets updates
Plan Human Resources Management Outputs - ANSWER Human Resources Management Plan
Acquire Project Team Outputs - ANSWER Project staff assignments
Resource calendars
PM Plan updates
Develop Project Team Outputs - ANSWER Team performance assessments
Enterprise environmental factor updates
Manage Project Team Outputs - ANSWER Change requests
PM Plan updates
Project doc updates
Enterprise environmental factors updates
Organizational process assets updates
Plan Communications Management Outputs - ANSWER Communications management plan
Project doc updates
Manage Communication Outputs - ANSWER Project Communications
PM Plan updates
Project doc updates
Organizational Process Assets Updates
Control Communications Outputs - ANSWER Work Performance information
Change requests
PM Plan updates
Project doc updates
Organizational process assets updates
Plan Risk Management Outputs - ANSWER Risk Management Plan
Identify Risks Outputs - ANSWER Risk Register
Perform Qualitative Risk Analysis Outputs - ANSWER Project doc updates
Perform Quantitative Risk Analysis Outputs - ANSWER Project doc updates
Plan Risk Responses Outputs - ANSWER PM Plan updates
Project doc updates
Control Risks Outputs - ANSWER Work performance information
Change requests
Project Management Plan updates
Project doc updates
Organizational process assets updates
Plan Procurement Management Outputs - ANSWER Procurement management plan
Procurement statement of work
Procurement documents
Sources selection criteria
Make-or-buy decisions
Change requests
Project documents updates
Conduct Procurements Outputs - ANSWER Selected sellers
Agreements
Resource calendars
Change requests
PM Plan updates
Project doc updates
Control Procurements Outputs - ANSWER Work Performance information
Change requests
PM Plan updates
Project doc updates
Organizational process assets updates
Close Procurements Outputs - ANSWER Closed procurements
Organizational process assets updates
Identify Stakeholders Outputs - ANSWER Stakeholder register
Plan Stakeholder Management Outputs - ANSWER Stakeholder management plan
Project doc updates
Manage Stakeholder Engagement Outputs - ANSWER Issue Log
Change requests
PM Plan updates
Project doc updates
Organizational process assets updates
Control Stakeholder Engagement Outputs - ANSWER Work performance information
Change requests
PM Plan updates
Project doc updates