• Question 1
3 out of 3 points
The manager of the Quick Stop Corner Convenience Store (which never closes) sells four cases of Stein beer each day. Order costs are $8.00 per order, and Stein beer costs $.80 per six
...
• Question 1
3 out of 3 points
The manager of the Quick Stop Corner Convenience Store (which never closes) sells four cases of Stein beer each day. Order costs are $8.00 per order, and Stein beer costs $.80 per six-pack (each case of Stein beer contains four six-packs). Orders arrive three days from the time they are placed. Daily holding costs are equal to 5 percent of the cost of the beer.
At what point should he reorder Stein beer?
• Question 2
3 out of 3 points
Ann Chovies, owner of the Perfect Pasta Pizza Parlor, uses 20 pounds of pepperoni each day in preparing pizzas. Order costs for pepperoni are $10.00 per order, and carrying costs are 4 cents per pound per day. Lead time for each order is three days, and the pepperoni itself costs $3.00 per pound. What is the economic order quantity for pepperoni?
• Question 3
3 out of 3 points
If no variations in demand or lead time exist, the ROP will equal:
• Question 4
3 out of 3 points
The materials manager for a billiard ball maker must periodically place orders for resin, one of the raw materials used in producing billiard balls. She knows that manufacturing uses resin at a rate of 50 kilograms each day, and that it costs $.04 per day to carry a kilogram of resin in inventory. She also knows that the order costs for resin are $100 per order, and that the lead time for delivery is four days. If order size was 1,000 kilograms of resin, what would be the length of an order cycle?
• Question 5
3 out of 3 points
A stock or store of goods is called a(n):
• Question 6
0 out of 3 points
A potential obstacle to conversion to a lean system is:
1.
2. (I) lack of management commitment
3. (II) lack of worker cooperation
4. (III) supplier resistance
5. (IV) insufficient space to store the increased inventories
• Question 7
3 out of 3 points
A production kanban card is used to signal that:
• Question 8
3 out of 3 points
Process design that supports lean does not include:
• Question 9
3 out of 3 points
A lean-systems method of asking questions about a process is the __________ approach.
• Question 10
3 out of 3 points
Which of the following does not contribute to reduced setup time and cost?
• Question 11
3 out of 3 points
_________ has/have helped firms to concentrate on their core business.
• Question 12
3 out of 3 points
Which of the following is not a measure of the reliability of the supply chain?
• Question 13
3 out of 3 points
After outsourcing to global suppliers, __________ is not simple.
• Question 14
3 out of 3 points
One of the biggest ethical risks in supply chain management is that the __________ supply chain member tends to be the one that suffers the blame and/or lost goodwill when something goes wrong.
• Question 15
3 out of 3 points
The website and order fulfillment are essential features of:
• Question 16
0 out of 3 points
The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants—Charlie, Betty, Johnny, and Rick—to complete any of the four projects, as follows:
Project (Hours)
Consultant A B C D
Charlie 13 16 11 13
Betty 11 15 14 18
Johnny 15 22 12 15
Rick 17 17 12 22
________________________________________
Assume there must be one-to-one matching between consultants and projects. What is the optimal assignment of consultants to projects?
• Question 17
3 out of 3 points
There are four resources and four jobs to be done. Assume there must be one-to-one matching between jobs and resources. The time required for each resource to do each job is as follows:
Job (Hours)
Resource A B C D
1 5 8 7 7
2 4 9 5 9
3 6 9 8 7
4 7 6 6 9
________________________________________
After the row reduction, what is the resulting entry in the new table for assigning resource 4 to Job D?
• Question 18
3 out of 3 points
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received:
Job Processing Time (hrs) Due
(hrs from now)
W 4 4
X 3 5
Y 2 2
Z 1 1
________________________________________
If he uses the first come, first served priority rule to schedule these jobs, what will be the average completion time?
• Question 19
3 out of 3 points
Scheduling pertains to:
• Question 20
3 out of 3 points
The two different approaches to load work centers in job-shop scheduling are:
• Question 21
3 out of 3 points
The fixed-order-interval model requires a continuous monitoring of inventory levels.
• Question 22
3 out of 3 points
Gatekeeping contracts with 3PLs to minimize the cost of shipping returned goods.
• Question 23
3 out of 3 points
Some firms have structured their procurement function to include both centralized and decentralized purchasing.
• Question 24
3 out of 3 points
Makespan is the total time needed to complete a group of jobs.
• Question 25
3 out of 3 points
Input/output (I/O) control refers to monitoring the productivity changes since productivity is determined by the ratio of output to input.