CLC 222 Mod 6 Special Considerations Exam
• Here is your test result.The dots represent the choices you have made.
• The highlighted questions are the questions you have missed.
• Remediation Accessed shows whether
...
CLC 222 Mod 6 Special Considerations Exam
• Here is your test result.The dots represent the choices you have made.
• The highlighted questions are the questions you have missed.
• Remediation Accessed shows whether you accessed those links.'N' represents links not visited and 'Y' represents visited links.
Back to Status page
contains 7 Questions
________________________________________
1) An Earned Value Management system that is formally validated and accepted by the cognizant contracting officer is required on cost or incentive contracts valued at or greater than ____. [Define EVM and cost performance reporting]
$50 million
$20 million
$100 million
$10 million
________________________________________
2) The American National Standards Institute/Electronic Industries Alliance (ANSI/EIA) established 36 management system guidelines that ensure and provide complete information needed to make management decisions. [Define the major actions required to evaluate the contractor’s engineering efforts and management systems] [Remediation Accessed :N]
False
True
________________________________________
3) According to the Davis Bacon Act (DBA), contractor employees shall be paid no less than the prevailing wage rates as determined by the Secretary of Labor and ____________. [Analyze the inspection clauses for fixed type and cost reimbursement contracts used in construction]
Employees shall be paid no less often than once a week.
Employees shall be given 30 days of leave a year.
Employees shall be paid at least once every two weeks.
Wage rates shall be available on site in the manager’s office files.
[Show More]