Case Study #2 (Using Agile Approach – Relocation Project)
Total points: 30
Group Assignment
Project description: You are hired by the SCM Faculty Coordinator to move old
offices of six SCM faculty/staff from the 3rd
...
Case Study #2 (Using Agile Approach – Relocation Project)
Total points: 30
Group Assignment
Project description: You are hired by the SCM Faculty Coordinator to move old
offices of six SCM faculty/staff from the 3rd floor (Hyland Hall) to new offices on the 4th
floor (Hyland Hall).
1. Items include books, computers, printers and other miscellaneous items.
Furniture such as desks, cabinets and bookshelves are not to be moved.
2. Unlimited boxes are available.
3. Unpacking boxes is not part of the project.
4. Offices on the 4th floor are move-in ready.
Office Estimated number
of boxes
Preferred deadline -
Handover of new office to
the client
#1 10 11:00 am
#2 10 12:00 pm
#3 10 2:30 pm
#4 10 11:00 am
#5 5 9:30 am
#6 5 8:30 am
Tasks and estimated task times are as follows:
Packing and labeling boxes - 6 minutes per box
Loading boxes into dolly - 1 minute per box
Moving loaded dolly (1 trip) from 3rd floor to 4th floor - 20 minutes.
Unloading boxes into offices - 1 minute per box
Moving empty dolly (1 trip) from 4th floor to 3rd floor - 10 minutes
Cleaning old offices – 15 minutes per office
Sprint meetings (face–to–face) – 15 minutes per meeting
#1) COMPLETE TABLES BELOW FOR STRATEGY #1. (15 points)
#2) COMPLETE TABLES BELOW FOR STRATEGY #2. (15 points)
NOTE: The following sources can provide definition and description of
concepts/terminology used in Agile Approach:
i. Agile Handbook, Taymor E. (available in Module: Agile Approach and Scrum
Framework in CANVAS).
ii. The Scrum Guide, Schwaber K. and Sutherland J. (available in Module: Agile
Approach and Scrum Framework in CANVAS).
iii. Agile Practice Guide, Published by Project Management Institute, 2017,
https://www.pmi.org/pmbok-guide-standards/practice-guides/agile