FINAL PROJECT
By Meghan Perry
Fundamentals of Power Systems
Due: 11/28/2018Table of Contents
1 Scope..…………………………………………………………………………………………………………………3
2 Design Specifications……………………..……………………………………………………..3
3 Design P
...
FINAL PROJECT
By Meghan Perry
Fundamentals of Power Systems
Due: 11/28/2018Table of Contents
1 Scope..…………………………………………………………………………………………………………………3
2 Design Specifications……………………..……………………………………………………..3
3 Design Process……………………….………………………………………………………….3
3.1 Base Case Contingency Violations….………………………………………………...4
3.2 Design 1………………..……………………………………………………………...4
3.3 Design 2……..………………………………………………………………………...6
3.4 Design 3……………………………………………………………………………….9
4 Cost Analysis……………….………………………………………………………..…..….....10
5 Conclusion……….…………………………………………………………………………….111 Scope
The completion of this course project will require an in-depth understanding of Chapters 1‒
6 of the textbook (J. D. Glover, T. J. Overbye, and M. S. Sarma, Power System Analysis &
Design, Six Edition. Cengage Learning, 2017)
2 Design Specifications
To implement the Metropolis Light and Power (MLP) server farm, we needed at least two
transmission lines exiting the substation to ensure stability and safety. The overall objective is to
not only find a solution to implement the TULIP substation into the system, but to also find the
cheapest addition costs. The costs per mile for a transmission line and transformers, if any, are
compared to the reduction in system loss due to the additions over a period of five years. This
cost analysis will weigh heavily in deciding which design would be more beneficial for the
addition of the TULIP substation. We must also complete the integration of the new server farm
without any contingency violations. The transmission systems should be designed to operate at
specific voltage levels, in this case 138/69kV and with certain current limits. If these limits and
voltage levels are outside a certain tolerance it will result in a contingency violation.
3 Design Process
3.1 Base Case Contingency Violations
To begin, we first needed to do a contingency analysis of the current system without the
TULIP substation. The initial system is shown in in Figure 1 below
[Show More]