Budget Analysis Report
Budget Analysis:
A budget analysis report is used to determine the relationship between money and
how a project is being managed. This report will also provided whether the budget is
sufficient
...
Budget Analysis Report
Budget Analysis:
A budget analysis report is used to determine the relationship between money and
how a project is being managed. This report will also provided whether the budget is
sufficient and practical to complete the project. Throughout a budget analysis report, the
budget will be evaluated to determine the financial state of a project. The budget analysis
report will also pull information from previous projects and their outcomes. The most
important step of completing a budget analysis report is determining failure points of the
project and propose turnaround project budgets.
Project Summary:
Nearly Free is an IT Governance company that is looking to build an employee
orientation learning module. This module will include at least one quiz and a sign off
document. All new employees must complete their orientation and understand the
information. This project has a budget of $25,000 and a timeline of about three months.
This project will include various steps such as planning, designing, development, testing,
changes, retest, and closeout. However, this project seems to be failing and going over
budget. This budget analysis report will help determine where the issue is and how to
turnaround this project.
Financial State:
After reviewing Nearly Free cost estimate techniques, it seems that the project
will go over budget. The budget for the employee training/orientation project is about
$30,000. In addition, with developing, integration, testing, training, controlling and
project closure still needing to be complete the project baseline is already at $22,000.
With the duties that still need to be completed and less than $10,000 left it the budget, it
seems that this project is going to go over budget and possibly miss important roles. By
being over budget this project may not succeed. This failure could be because of using
analogous cost data estimating or parametric estimating with poor data. These costs
estimates should be completed early in the project and provide a total cost. The analogous
estimates require little data, which can be inaccurate. The parametric estimates compare
the relationship between two or more variables to determine cost. These estimates are
quick and easy but may not be accurate. Lastly, the top down estimate is used to estimate
where each task is allocated then determine where it falls within the project estimate. This
would be the most beneficial technique to use for Nearly Free.
Cost of Individual Schedule Activities/WBS