CLE 003 Technical Reviews Exam 100%
1. Technical reviews should be event driven not schedule driven with clear-cut entry and exit
criteria
2. True False 11) As a best practice, who is responsible for tailoring IEEE St
...
CLE 003 Technical Reviews Exam 100%
1. Technical reviews should be event driven not schedule driven with clear-cut entry and exit
criteria
2. True False 11) As a best practice, who is responsible for tailoring IEEE Standard 15288.2
for Technical Reviews and Audits on Defense Programs and making available a data
repository and how far in advance of the technical review are these tasks performed?
1. Which of the following statements is true?
The overarching reason for integrating technical reviews into the acquisition life cycle is
to successfully complete the Operational Testing (OT) of the system under review.
The overarching reason for integrating technical reviews into the acquisition life cycle is
to successfully complete Developmental Testing of the system under review.
The overarching reason for integrating technical reviews into the acquisition life
cycle is to design, develop, and field systems that meet the contractual
specifications and performance requirements of the warfighter.
The overarching reason for integrating technical reviews into the acquisition life cycle is
to successfully complete Developmental Testing of the system under review
2. As best practice, who is responsible for tailoring IEEE Standard 15288.2 for Technical
Reviews and Audits on Defense Programs and making available a data repository and how far
in advance of the technical review are these tasks performed?
IPT Systems Engineer and IPT Logistician, no later than three months prior to the
technical review.
Government Program Manager, no later than three months prior to the technical review.
Recorder, no later than three months prior to the technical review.
Government Program Manager, no later than two months prior to the technical review.
3. Which of the following will be assessed by the technical review board
Technical risks
Schedules, cost and performance risk
Technical risks
All of the items here will be assessed during each technical review
Technical design maturity
This study source was downloaded by 100000823742721 from CourseHero.com on 05-26-2022 17:39:02 GMT -05:00
https://www.coursehero.com/file/56675247/CLE-003-Technical-Reviews-Exam-100docx/4. Which of the following statements is
false
?
Prior to the technical review, the technical review board chairperson directs the
IPT systems engineer to complete all Request for Action forms to satisfy the
technical review entry criteria.
The three critical deliverables resulting from each technical review are the completed
Request for Actions forms, the updated Risk Assessment, and the recommendation to
the Program Manager as to the technical readiness of the program to enter the next
phase of development.
During the technical review, the tailored IEEE Standard 15288.2 for Technical Reviews
and Audits on Defense Programs structure may be followed with each technical review
board member responsible for evaluating his/her area of expertise.
No later than one month following the technical review, the technical review board
chairperson, IPT Systems Engineer, and IPT Logistician
5. Which of the following statements is
false
?
Tailoring of the 15288.2 should be led by the Integrated Product Team (IPT) Systems
Engineer and IPT Logistician
As a DoD adopted standard, the IEEE 15288.2 may be invoked by the government on
an contract.
The IEEE 15288.2 can only be tailored by deleting criteria that does not apply to
the system under development. Modification of criteria is not permitted.
The IEEE 15288.2 should be tailored by removing or modifying existing criteria and/or
adding new criteria, as applicable, to reflect the specific nature of the program.
6. Technical reviews should be event driven, not schedule driven, with clear-cut entry and exit
criteria.
True
False
This study source was downloaded by 100000823742721 from CourseHero.com on 05-26-2022 17:39:02 GMT -05:00
https://www.coursehero.com/file/56675247/CLE-003-Technical-Reviews-Exam-100docx/7. Which of the following statements is
true
?
The System Verification Review (SVR) is conducted to ensure that the subsystem,
system, or system under review is ready to proceed into formal test.
The Physical Configuration Audit (PCA) is conducted to ensure that the system under
review
can proceed into detailed design.
System Functional Review (SFR) is conducted to determine the current technology
readiness level of selected system elements
Production Readiness Review (PRR) is an examination of the product to determine
if the design is ready for production and the producer has accomplished adequate
production planning
8. Which of the following is NOT a typical technical review exit criteria consideration that applies
to most technical reviews?
Are all of the requirements for certification of readiness for the Operational
Testing (OT) completed?
Are the risks known and manageable for design and development?
Is the program properly staffed?
Is the program executable within the program budget?
9. Which of the following is true?
Integrated Product Team (IPT) briefer may be invited to provide expert briefings of
each of the relevant technical subjects to address during the technical review.
Independent subject matter experts (SMEs) are included only in the later technical
reviews, starting with the Preliminary Design Review (PDR).
Government counsel, user representative, and development and operational testers
must be include every technical review.
The program manager should always perform the role of Technical Review Board
chairperson.
10. An agreed upon test configuration system, test plans, test cases, and test procedures are
common entry criteria for which of the technical reviews?
Test Readiness Review (TRR)
Test Readiness Assessment (TRA)
This study source was downloaded by 100000823742721 from CourseHero.com on 05-26-2022 17:39:02 GMT -05:00
https://www.coursehero.com/file/56675247/CLE-003-Technical-Reviews-Exam-100docx/Preliminary Test Review (PTR)
Developmental Test Review (DTR)
11. Which of the following statements is true?
While the average amount of time the typical technical review lasts is two or three
days, the duration varies widely based on the size and complexity of the program
being reviewed.
Technical reviews are usually held at the prime contractor's facility.
It is recommended that each technical review be conducted one month before the
program milestone or event it supports.
It is recommended that for large, complex programs, the subsystem technical reviews be
conducted jointly with the system technical reviews.
12. Which of. the following statements is true about the technical review "AFTER Risk
Assessment Checklist"?
•At the end of the review, the IPT System Engineer documents follow-up actions
resulting from the technical review in the AFTER Risk Assessment Checklist
CLE 003 Technical Reviews test
1) Which of the following statements is true?
The Integrated Baseline Review (IBR) is conducted well in advance of the actual cost estimate submission to
support the program's initial POM (Program Objective Memorandum) submission.
The Critical Design Review (CDR) is conducted well in advance of Milestone B to ensure that the system under
review can proceed into the System Development and Demonstration phase.
The Alternative Systems Review (ASR) is conducted in advance of Milestone A to demonstrate that the
preferred concept is ready to move into the Technology Development phase.
The In-Service Review (ISR) is an examination of the product conducted to determine if the design is ready for
production and the producer has accomplished adequate production planning.
Which of the following statements is false?
The three critical deliverables resulting from each technical review are the completed Request for Actions
forms, the updated Risk Assessment, and the recommendation to the Program Manager as to the technical
readiness of the program to enter the next phase of development.
During the technical review, the tailored IEEE Standard 15288.2 for Technical Reviews and Audits on Defense
Programs structure may be followed with each technical review board member responsible for evaluating
his/her area of expertise.
During the technical review, the technical review board chairperson decides which
Requests for Action will be declined.
No later than one month following the technical review, the technical review board chairperson, IPT Systems
Engineer, and IPT Logistician should review the results of assessing the program against IEEE Standard
15288.2 tailored acceptability criteria.
3) Which of the following statements is true?