CPIM(Certified In Production & Inventory Management)
- 1 -
BSCM Sample TEST.
1. Which of the following demand fulfillment approaches typically provides the longest delivery time ?
A) Engineer-to-order. B) Make-to-ord
...
CPIM(Certified In Production & Inventory Management)
- 1 -
BSCM Sample TEST.
1. Which of the following demand fulfillment approaches typically provides the longest delivery time ?
A) Engineer-to-order. B) Make-to-order.
C) Assemble-to-order. D) Make-to-stock.
2. Which of the following is generally a characteristic of a product-focused layout ?
A) Large queues at workstations. B) Fixed flow of work.
C) Production to a work order. D) General purpose workstations.
3. Which of the following is generally a function of the physical distribution system ?
A) Production activity control. B) Production planning.
C) Packaging. D) Bill of material.
4. Forecasts are typically more accurate for the near future than they are for the longer future. This
occurs because
A) The near term holds less uncertainty than the long term.
B) More data is available in the near term.
C) Aggregate data is easier to forecast.
D) The future is more dynamic in the near term.
5. A forecast is typically more accurate for
A) Groups of items rather than for individual items.
B) Daily rather than monthly periods of time.
C) Physical units rather than monetary units.
D) Far out in the future rather than nearer time periods.BSCM Sample TEST
- 2 -
6. An anticipated build schedule can be BEST described as
A) Production plan. B) Capacity plan.
C) Materials requirements plan. D) Master production schedule.
7. Which of the following is MOST likely to be a dependent demand item ?
A) A manufactured subassembly. B) An item in a grocery store.
C) A service part. D) An office supply item.
8. Which of the following manufactured product types are BEST suited for flow manufacturing ?
A) Wide range of disparate products.
B) Limited range of similar products.
C) Low volume of similar products.
D) High volume of disparate products.
9. The master production schedule is generally a direct input to
A) Production planning. B) Material requirements planning (MRP).
C) Purchasing planning D) Production activity control (PAC).
10. A company needs to produce 4000 units over the next two months. There are 21 working days in the
first month and 19 working days in the second month. What must the daily rate be with a level strategy
?
A) 50 B) 75 C) 100 D) 125
11. The portion of a company's inventory and planned production which is not already committed is
A) Inventory allocation. B) Inventory commitment.
C) Available to promise. D) Multi-plant planning
[Show More]