unit 5 Probability of Project Completion
Probability of Project Completion
For a project, Z was calculated as 0.35, the probability of the target
completion is __________.
6
...
Colorado Technical University
MATH 451
unit 5 Probability of Project Completion
Probability of Project Completion
For a project, Z was calculated as 0.35, the probability of the target
completion is __________.
63%
63.31%
63.68% or 64%
35%
The target completion time for a project with an expected completion time of
13 weeks and project standard deviation of 1.15 is __________ with a 90%
certainty.
14.0 weeks
14.5 weeks or (13 + 1.28 * 1.15) weeks
13.5 weeks
16.4 weeks
PERT makes the assumption that __________.
the activity times are statistically dependent
the total project completion times do not follow a normal probability distribution
the total project completion times follow a normal probability distribution
the activity times follow a normal probability distribution
The variance of the complete project is computed by summing the variances
of the activities on the __________.
project
critical path
noncritical path
project network
Z is the number of __________ the target completion time lies from the
expected completion time.
weeks
variances
standard deviations
distributions
Given the following activities for a project, with the critical activities in red,
the project standard deviation is __________.
√(0.22 + 0.36 + 1.00) or 1.97
1.26
√(0.22 + 0.25 0.36)
√0.22 + √0.25 + √1.00
The bell-shaped normal curve represents the project completion dates, and
there is a 50% chance of completing __________ the expected completion.
on
around
prior to
near
The variance of the complete project is computed by summing the variances
of the activities on the __________.
project network
noncritical path
project
critical path
Given the following activities for a project, with the critical activities in red,
the project variance is __________.
0.83
0.22 + 0.25 + 0.36
1.83
0.22 + 0.36 + 1.00
The __________ is the square root of the project variance.
activity standard deviation
activity variance
project time estimate
standard deviation of the project
Z is the number of __________ the target completion time lies from the
expected completion time.
standard deviations
distributions
weeks
variances
Given the following activities for a project, with the critical activities in red,
the project standard deviation is __________.
√1.58 or 1.26
2.07
1.35
0.47 + 0.60 + 1.00
For a project with an expected completion time of 25 weeks, a target
completion of 24 weeks, and project standard deviation of 1.21 weeks, Z
score is __________.
0.82
(24 - 25) / 1.21
0.83
(25 - 24) / 1.21
project standard deviation of 1.75 is __________ with a 99% certainty.
24.7 weeks
39.1 weeks
20.2 weeks
24.1 weeks or (20 + 2.33 * 1.75) weeks