Contains 21 Questions (Attempt=1/3)
Module 4 Exam
1) Which 14-Point Schedule Metric verifies that all tasks with durations greater than zero
have dollars or hours assigned? 4.8 pg. 18 of 40
Baseline Execution Index (
...
Contains 21 Questions (Attempt=1/3)
Module 4 Exam
1) Which 14-Point Schedule Metric verifies that all tasks with durations greater than zero
have dollars or hours assigned? 4.8 pg. 18 of 40
Baseline Execution Index (BEI)
High Float
Resources
Leads
2) In a Gantt chart, which of the following is signified as a simple, solid bar with distinct
start and finish designators? 4.4 pg. 9 of 73
Summary Task
Non-Critical Task
Critical Task
Summary Task, In Progress
3) Which of the following is a viable solution to schedule time constraint issues?
4.6 pg. 12 of 63
Accepting a shorter length of time for the project
Shortening task durations for tasks on the critical path
Cutting resources
Adding more tasks to the critical path
4) Consider the characteristics of the three types of network schedules: Program
Evaluation and Review Technique (PERT), Arrow Diagram Method (ADM), and
Precedence Diagramming Method (PDM). Which of the following is a true statement?
1
10162577 1
10162545 1
10162563 1
4.4 pg. 54 of 73
PDM was developed to overcome the disadvantages of PERT and ADM, and doesn't treat
all task relationships as "Finish-to-Start (FS)."
All three types of network schedules rely on time estimates for each activity to build an
accurate schedule.
PERT and PDM use the FS task relationship while ADM can use any type of task
relationship.
PDM and ADM are seldom used due to the increase of computer-based scheduling tools.
5) In which step of the Schedule Development and Management Process do you identify
the quantity and types of labor categories required to complete a task?
Determine Resource Requirements
Identify Tasks
Monitor and Control Program Schedule
Estimate Task Duration
6) Which schedule type is also referred to as a bar chart since it depicts a task as a
horizontal bar imposed over a time line or calendar?
Internal schedule
Gantt chart
Milestone chart
Network diagram
7) A proposal manager asks the team to provide "80%" estimates for their schedule. The
team believes that they have an 80% chance of finishing on time, when in reality, they do
not. In this example, the team clearly does not take into account the overall uncertainty of
the program. Which of the following causes for schedule risks and delays is being
described? (VERBATIM) 4.7 pg. 25 of 38
10162553 1
10175089 1
10162542 1
10162570 1
Incorrect schedule relationships or logic
Uncertainty in task duration estimates
Unrealistic milestones or deadlines
Inability to change the number of tasks
8) The detailed tasks required to be completed and identified in the time-based Integrated
Master Schedule (IMS) are directly linked to what element of the event-based Integrated
Master Plan (IMP)?
Accomplishment
Assignment
Event
Criteria
9) Which of the following components of the Precedence Diagramming Method (PDM) is
identified by expanding the schedule to display the Start and Finish columns?
Earliest and Latest Start and Finish Dates
Task identifiers
Float/Slack
Critical Path
10) Which of the following are characteristics of the forward pass, one of the components
of the Critical Path Method (CPM)? (Select three that apply.)
Results in the earliest start dates for all the tasks
Continues to the last task in accordance with task relationships
Begins with the first task in the schedule
10175085 1
10162556 1
10162559 6
Results in the latest finish dates for all the tasks
11) Which schedule resource constraint solution is best used when there is a program
benefit to using resources other than those originally planned?
Adding resources
Adjusting the schedule to accommodate slack
Reducing program scope
Substituting resources
12) Which schedule duration estimating method uses statistical relationships determined
from historical data to calculate the estimate for certain tasks? 4.10 pg. 14 of 42
Parametric Estimate
Single-Point Estimate
Analogous Estimate
Three-Point Estimate
13) How are schedules in a schedule change management system similar to project
elements under configuration management (CM)?
In both a schedule change management system and CM, the first version is used
consistently throughout the entire project.
In both a schedule change management system and CM, each version needs to be
managed, controlled, and constantly monitored.
In both a schedule change management system and CM, changes to versions can be made
without notifying team members.
In both a schedule change management system and CM, versions are monitored only by
the program manager (PM).
14) When is Agile Project Management typically used during the scheduling process?
10162568 1
10162532 1
10162536 1
4.10 pg. 20 of 42
When the schedule is stable and low-risk
When the schedule requires only one sprint
When requirements are likely to be fixed throughout the entire project
When requirements are likely to change as the project progresses
15) Consider the differences between a resource-constrained schedule and a timeconstrained schedule. Which constraint occurs when there is a shortage of people,
equipment, facilities, or materials; and which constraint occurs when the length of the
critical path surpasses the allotted time for the project? 4.6 pg. 11 of 53
Resource constraint, schedule constraint
Management constraint, time constraint
Time constraint, resource constraint
Resource constraint, time constraint
16) Prior to using the 14-Point Schedule Metrics, the number of each type of the four
relationships (Finish-to-Start [FS], Finish-to-Finish [FF], Start-to-Start [SS], and Start-toFinish [SF]) for incomplete tasks needs to be calculated. This describes which of the
following data types? 4.10 pg. 37 of 42
Incomplete Tasks
Baseline Count
Relationship Count
Complete Tasks
17) Which of the following are advantages of network diagrams? (Select three that apply.)
4.4 pg. 71 of 73
Generally useful for information briefings and reviews
10162539 1
10162561 1
10162574 1
10162549 6
Enables early detection of resource constraints
Graphically depicts the relationship between project activities/events and their impacts
Allows planners to do quick "what if" analyses of changes to the schedule
18) Which task dependency is the most common type of schedule relationship and
involves a successor not being able to start until the predecessor finishes? 4.3 PG. 19 of 80
Start-to-Finish (SF)
Finish-to-Start (FS)
Start-to-Start (SS)
Finish-to-Finish (FF)
19) After starting the Schedule Development and Management Process by identifying a
comprehensive list of program tasks, assigning identifiers, and including additional
information such as potential constraints, what sort of product should the program
manager (PM) expect to have? 4.3 pg. 13 of 80
A visual representation of the task list showing the sequencing of each task and the listing
of all tasks in a work package
A visual representation of the task list showing all available float for each task and the
listing of all tasks in a task list
A visual representation of the task list showing all resources needed for each task and the
listing of all tasks in a control account
A visual representation of the task list showing the breakdown of work packages into
tasks and the listing of all tasks in a task list
20) What are the first three steps in the process for building a Precedence Diagramming
Method (PDM) schedule? 4.5
Estimate task durations, determine resource requirements, sequence the tasks
10162525 1
10162529 1
10162579 1
Sequence the tasks, identify the tasks, estimate task durations
Identify the tasks, sequence the tasks, determine resource requirements
Determine resource requirements, estimate task durations, identify the tasks
21) The summary schedule is generally associated with levels 1-3 of the Work Breakdown
Structure (WBS), whereas the intermediate schedule is generally associated with which
WBS levels? 4.3 pg. 61 of 80
Levels 2-3
Levels 2-5
Levels 3-4
Levels 3-5
10162534 1
[Show More]