Management > QUESTIONS & ANSWERS > PMT 252 PMT 252 Mod 4 test | Defense Acquisition University (All)
PMT 252 Mod 4 1. Which of the following is a viable solution to a schedule resource constraint? a. Conducting some task concurrently b. Substituting resources 2. Consider the differences between a... time-constrained schedule and a resource-constrained schedule. Which constraint occurs due to limitations imposed by the length of time or dates in a schedule, and which constraint occurs when the number and/or type of support required is greater than the number available? a. Time constraint, resource constraint 3. What is the difference between a summary schedule and a detailed schedule? a. Summary schedules tie, or roll up, the detailed schedule to key events and milestones in the summary schedule(s); whereas detailed schedules graphically depict the contractually required events and milestones to accomplish program objectives. b. Summary schedules graphically depict the contractually required events and milestones to accomplish program objectives, whereas detailed schedules graphically depict the effort at the work package and planning package level. 4. Which of the following are characteristics of the use of Agile Project Management in scheduling? (Select 2 that apply) a. Work closely / Prepare traditional 5. Which of the following does the last step of the Schedule Development and Management Process, Monitor and Control Program Schedules, entail? (Select 2) a. Assigning/Determining 6. Which schedule type is also referred to as a bar chart since it depicts a task as a horizontal bar imposed over a time line or calendar? a. Gantt chart 7. Consider the differences between the Program Evaluation and Review Technique (PERT) and Arrow Diagram Method (ADM) network schedules. Which of the following is a true statement? a. PERT uses three time estimates while ADM uses only one time estimate. 8. What is the result of the Identification of Schedule Tasks step in the Schedule Development and Management Process? a. A comprehensive list of all tasks to be performed for the program. 9. Which of the following are characteristics of the forward pass, one of the components of the Critical Path Method (CPM)? (Select three that apply) a. Results in the earliest start dates for all tasks/ Begins with the first task in the schedule / Continues to the last task in accordance with task relationships. 10. Which of the following are disadvantages of network diagrams? (Select two that apply). a. Difficult to conduct “what if” / May be too difficult to graphically portray large projects 11. How does the IMS relate to the IMP? a. The IMP is a high-level document that identifies the tasks to be accomplished while the IMS breaks down the tasks into actionable items. b. The IMS provides a more detailed description of the tasks identified in the IMP. c. The IMS identifies the time frames to be used in the development of the IMP. 12. Which task dependency involves the successor not being able to finish until the predecessor finishes? b. Finish-to-Start 13. In the Precedence Diagramming Method (PDM) schedule, the critical path is delineated by red bars, float/slack are identified in the Total Slack and Free Slack columns, and the earliest and latest start and finish dates are identified in which of the following? a. Start and Finish columns 14. Which schedule duration estimating method considers the optimistic estimate, the pessimistic estimate, and the most likely estimates? a. Three-point estimate 15. A new team leader thinks that there are too many links in the schedule. So, he decides to remove many of them in attempts to shorten the schedule and make it simpler. What he fails to realize, however, is that most of the links were valid; as a result of his hasty changes, his program is now delayed. Which of following causes for schedule risks and delays is being described? a. Inability to change the number of tasks. b. Incorrect schedule relationships or logic 16. How are schedules in a schedule change management system similar to project elements under configuration management (CM)? a. In both a schedule change management system and CM, each version needs to be managed, controlled, and constantly monitored. 17. Prior to using the 14-Point Schedule Metrics, the total number of tasks with detail level work (i.e., lowest level discrete tasks) needs to be calculated. This describes which of the following data types? a. Baseline Count b. Total tasks 18. In a Gantt chart, which of the following is signified as a simple, solid bar with distinct start and finish designators? a. Summary Task 19. What are the first three steps in the process for building a Precedence Diagramming Method (PDM) schedule? a. Sequence the tasks, identify the tasks, and estimate task durations 20. Which of the following is a viable solution to schedule time constraint issues? a. Accepting a shorter length of time for the project. 21. Which 14-Point Schedule metric measures the number of incomplete tasks with a total float greater than 44 working days? a. High Float 22. Which schedule time constraint solution is best used when the project has some flexibility in the end date and a long time to complete the project can be accommodated? a. Accepting a longer length of time for the project. 23. In which step of the Schedule Development and Management Process do you identify the quantity and types of labor categories required to complete a task? a. Determine Resource Requirements 24. Which of the following is valid guideline towards maintaining a good schedule change management system? a. Establish the process for submitting, evaluating, and approving changes. [Show More]
Last updated: 7 months ago
Preview 1 out of 4 pages
Buy this document to get the full access instantly
Instant Download Access after purchase
Buy NowInstant download
We Accept:
Can't find what you want? Try our AI powered Search
Connected school, study & course
About the document
Uploaded On
Sep 28, 2022
Number of pages
4
Written in
This document has been written for:
Uploaded
Sep 28, 2022
Downloads
0
Views
98
In Scholarfriends, a student can earn by offering help to other student. Students can help other students with materials by upploading their notes and earn money.
We're available through e-mail, Twitter, Facebook, and live chat.
FAQ
Questions? Leave a message!
Copyright © Scholarfriends · High quality services·