A configuration management program should focus on ensuring designs are
traceable to capability needs, developmental changes are controlled and
documented, interfaces are well-defined and understood, and
_____________
...
A configuration management program should focus on ensuring designs are
traceable to capability needs, developmental changes are controlled and
documented, interfaces are well-defined and understood, and
_______________________________. Correct Answer: All product
documentation is consistent with its supporting information.
Which technical review is held during the Technology Maturation and Risk
Reduction phase to ascertain progress in defining system technical requirements?
Correct Answer: System Requirements Review (SRR)
Program cost increases and schedules slips are most likely caused by
__________________, changes to the design, and changes to the production
processes. Correct Answer: Changes to user capability needs.
What group is used to help control the configuration of external interfaces for a
system? Correct Answer: Interface Control Working Group
Your new-start program was approved this year's Authorization Bill and you are
currently operating under Continuing Resolution Authority. To avoid losing a top
engineering from your program, you authorial the Contractor to begin work since
you expect the Appointment Bill to be signed next week. You are now in conflict
with the _____. Correct Answer: Anti-Deficiency Act
Cost, schedule, and performance parameters are interrelated and a change in one
parameters can affect the others. Therefore it is important to involve all the key
stakeholders when considering changes to Acquisition Program Baseline (APB).
Correct Answer: True
The Joint Interoperability Test Command (JITC) verifies ________________
through the field assessment of systems during exercises and contingencies, and
provides certificates of _____________ upon validation. Correct Answer:
Interoperability performance/ interoperability.
Which of the following configuration baselines provides the details from which a
contractor can transition from design to production of a system? Correct Answer:
Product Baseline