Problem 11-5
Manager T. C. Downs of Plum Engines, a producer of lawn mowers and leaf blowers, must develop an aggregate plan given the forecast for engine demand shown in the table. The department has a normal capacity
...
Problem 11-5
Manager T. C. Downs of Plum Engines, a producer of lawn mowers and leaf blowers, must develop an aggregate plan given the forecast for engine demand shown in the table. The department has a normal capacity of 130 engines per month. Normal output has a cost of $60 per engine. The beginning inventory is zero engines. Overtime has a cost of $90 per engine.
a. Develop a chase plan that matches the forecast and compute the total cost of your plan. (Negative amounts should be indicated by a minus sign. Leave no cells blank - be certain to enter "0" wherever required. Omit the "$" sign in your response.)
b. Compare the costs to a level plan that uses inventory to absorb fluctuations. Inventory carrying cost is $2 per engine per month. Backlog cost is $90 per engine per month. (Negative amounts should be indicated by a minus sign. Leave no cells blank - be certain to enter "0" wherever required. Omit the "$" sign in your response.)
Problem 11-6
Manager Chris Channing of Fabric Mills, Inc., has developed the forecast shown in the table for bolts of cloth. The figures are in hundreds of bolts. The department has a normal capacity of 275(00) bolts per month, except for the seventh month, when capacity will be 250(00) bolts. Normal output has a cost of $40 per hundred bolts. Workers can be assigned to other jobs if production is less than normal. The beginning inventory is zero bolts.
a. Develop a chase plan that matches the forecast and compute the total cost of your plan. Overtime is $60 per hundred bolts. (Negative amounts should be indicated by a minus sign. Leave no cells blank - be certain to enter "0" wherever required. Omit the "$" sign in your response.)
b. Would the total cost be less with regular production with no overtime, but using a subcontractor to handle the excess above normal capacity at a cost of $50 per hundred bolts? Backlogs are not allowed. The inventory carrying cost is $2 per hundred bolts. (Round your Average values to 1 decimal place. Negative amounts should be indicated by a minus sign. Leave no cells blank - be certain to enter "0" wherever required. Omit the "$" sign in your response.)
Problem 11-9
Wormwood, Ltd., produces a variety of furniture products. The planning committee wants to prepare an aggregate plan for the next six months using the following information:
Subcontracting can handle a maximum of 10 units per month. Beginning inventory is zero. Develop a plan that minimizes total cost. No back orders are allowed. (Negative amounts should be indicated by a minus sign. Leave no cells blank - be certain to enter "0" wherever required. Omit the "$" sign in your response.)
Problem 11-14
Refer to Example 3 in the textbook. Given the following information set up the problem in a transportation table and solve for the minimum-cost plan: (Omit the "$" sign in your response.)
Problem 11-19
Prepare a master production schedule for industrial pumps in the manner of the following table. Use the MPS rule to "schedule production when the projected on-hand inventory would be less than 10 without production." Suppose that a production lot size of 70 pumps is used. (Leave no cells blank - be certain to enter "0" wherever required.)