Q1 - SEP/DEC 2015 – P5
1 Iron Chicken (IC) is a multinational business which manufactures commercial building control systems. Building
control systems include heating and air-conditioning systems, lighting controls, p
...
Q1 - SEP/DEC 2015 – P5
1 Iron Chicken (IC) is a multinational business which manufactures commercial building control systems. Building
control systems include heating and air-conditioning systems, lighting controls, power and water monitoring and
security systems (e.g. keypad access, alarms and CCTV). IC’s manufacturing takes place at a number of factory sites
where some products have a long product life and are simple and mass-produced while other products are complex
and have a short product life due to changing technologies. IC’s mission statement is ‘to create value for shareholders
through control products which improve productivity, save energy and increase comfort and safety’.
A new chief executive officer (CEO) has been appointed to address a decline in IC’s share price in the last three years.
This CEO has identified that the business has grown through acquisition and as a result she stated, ‘senior
management have focused on making corporate deals and not making control systems.’ The CEO has declared that
the business must focus on optimising its value generation rather than just getting larger through acquisitions.
You are a performance management expert within IC. The CEO has tasked you with aiding her in aspects of her
improvement programme. First, she wants your views on the use of EVA™ as the key performance metric at IC. You
have been supplied with the current EVA™ calculation (Appendix 1) but there is some doubt about whether the junior
management accountant who has done this work was sufficiently trained in the method. So, the CEO needs you to
evaluate its accuracy and the assumptions which form part of the calculation.
Second, the CEO believes that the poor performance of the company can be addressed by ensuring that the mission
statement flows down into the performance management of the business. To that end, the following critical success
factors (CSFs) have been identified and the CEO wants you to suggest additional key performance indicators (KPIs)
for these.
CSF Associated current KPI
1. Greaterstaff productivity Units produced per labour hour
2. Reduction of wastage in production Power consumed per unit produced
3. Greater innovation of products Number of new products launched
Your suggestions should be in addition to these current KPIs.
Third, in order to improve performance, the CEO plans to implement initiatives associated with ‘lean’ manufacturing.
Specifically, there are three projects which have been suggested and the CEO needs your advice on these:
1. Move to just-in-time manufacturing
2. Use kaizen costing
3. Examine the costs of quality in achieving a ‘zero defects’ approach to manufacturing
The CEO has stated, ‘I need to know briefly how the improvement projects will meet the three CSFs and also how
they will impact on the existing three KPIs.’
Finally, the CEO requested, ‘You must tell me the implications of the improvement projects for our information systems
as I feel that they are not currently suitable for the plan that I have.’ The current information systems of the company
are based around the functional departments of the business such as manufacturing, marketing, finance and logistics.
Each department has developed its own system although all feed into the finance system which is the main one used
for strategic decision-making. In order that the department systems can all feed through to the current finance system,
these current systems only handle quantitative data. The company is considering the implementation of a new
information system. This new system will introduce networking technology in order to bring together all of the
departmental systems into a new, single, corporate database.
2 | Page
Required:
Write a report to the CEO of Iron Chicken to:
(i) Evaluate the accuracy of the EVA™ calculation and the assumptions in Appendix 1. Advise the CEO on your
results, providing calculations as needed. (15 marks)
(ii) For each of the three critical success factors at IC, briefly explain a weakness of the current KPI associated
with that CSF and then provide a justified alternative KPI. (6 marks)
(iii) Explain what the three improvement projects are, how they will help to meet the CSFs at IC and comment
on the impact of each project on the existing three KPIs. (15 marks)
(iv) Assess the impact of the proposed, new information system on the three improvement projects.
(10