Question 1
2 out of 2 points
A pre-solicitation conference will be held next month and you are preparing the synopsis to be
posted on FEBBIZOPPS. A draft RFP wil
...
CON 280 Exam 1 Answers provided 100% Complete solution
Question 1
2 out of 2 points
A pre-solicitation conference will be held next month and you are preparing the synopsis to be
posted on FEBBIZOPPS. A draft RFP will be posted with the synopsis with a note that
conference attendees will be given a CD containing RFP attachments comprising very large,
numerous technical files that could not be posted on the internet. Since the program office
manages the technical files, the program manager tasked her technical specialist, John Smith,
to produce the CDs for distribution at the conference. For those potential offerors or potential
subcontractors who cannot attend the pre-solicitation conference but want to request the CD,
which person do you identify as the point of contact in the synopsis?
Selected
Answer:
d.
The Contracting Officer
Answers: a.
The technical specialist
b.
The Program Manager
c.
No one. The Government is not required to provide information to a company
that elects not to attend the pre-solicitation conference.
d.
The Contracting Officer
Response Feedback: That is correct!
Question 2
2 out of 2 points
The contracting officer has been tasked to assist the Program Manager in writing an acquisition
plan for a multi-million dollar services acquisition. Select the item that would be included in the
Acquisition Plan.
Selected
Answer:
a.
Market research information that includes a list of potential sources as well
as estimated costs
Answers: a.
Market research information that includes a list of potential sources as well
as estimated costs
b.
Proposal content, including page limitations and font size.
c.
Detailed technical discussion of what is required and how the specification
addresses this requirement.
d.
Evaluation criteria that will be used in the source selection.
Response Feedback: That is correct!
Question 3
2 out of 2 points
When should acquisition planning begin?
Selected Answer: c.
As soon as the agency need is identified
Answers: a.
When the requirement is received and accepted by the Contracting Officer
b.
When a Source Selection Authority has been identified
c.
As soon as the agency need is identified
d.
When certified funds become available
Response Feedback: Correct
Question 4
2 out of 2 points
You have been tasked to assist the Program Manager on your Integrated Product Team (IPT) to
write a formal acquisition plan for multi-million dollar services acquisition. As the lead
procurement expert on the IPT, where will you find guidance on what should be included in
the Acquisition Plan?
Selected Answer: a.
FAR 7.105
Answers: a.
FAR 7.105
b.
FAR part 9
c.
FAR part 10
d.
FAR part 7
Response Feedback: Correct
Question 5
2 out of 2 points
At a minimum, the Market Research Report should:
Selected Answer: c.
All of the above.
Answers: a.
Explain the needs driving the acquisition
b.
Identify sources contacted
c.
All of the above.
d.
Identify the team members
Response Feedback: That is correct!
Question 6
2 out of 2 points
You are planning for the procurement of an advanced, engineering or operational systems
development and first production. The uncertainties of performance are such that they
preclude use of a fixed-price type contracts. However, they may not be so great as to justify use
of a cost-plus-a-fixed-fee contract. In these circumstances, what contract type should be used?
Selected Answer: c.
Cost Plus Incentive Fee
Answers: a.
Fixed Price Incentive Firm
b.
Fixed Price with Economic Price Adjustment
c.
Cost Plus Incentive Fee
d.
Cost Plus Award Fee
Response Feedback: That is correct!
Question 7
2 out of 2 points
Market research conducted for an upcoming requirement (estimated at $62.7 million over five
years) revealed that there is only one small business that may be capable of performing the
contract in its entirety. In the past, there have been many smaller contracts, which were
focused on supporting individual base functions. The new contract will consolidate many of
those functions under a single award and will result in substantial cost savings and benefits to
the Government. Previously, the smaller contracts were all accomplished by small businesses.
The market research report shows that there are eight large firms capable of performing the
entire contract, and approximately 55 small businesses that can perform portions of the work.
How should the acquisition team proceed?
Selected
Answer:
b.
Conduct a full and open competition.
Answers: a.
Return to the previous acquisition strategy and award individual smaller
contracts again.
b.
Conduct a full and open competition.
[Show More]