Sophia Project Management
Unit 1- Challenge 1 & 2
1 — Project Management
Which of the following activities would be considered an operation?
Prepare agendas for monthly faculty meetings
Which of the following activi
...
Sophia Project Management
Unit 1- Challenge 1 & 2
1 — Project Management
Which of the following activities would be considered an operation?
Prepare agendas for monthly faculty meetings
Which of the following activities would be considered a project?
Organize an all-staff event to introduce a new principal
Which of the following statements about projects is true?
Projects typically have managers in charge of leading the work.
2 — Project Stakeholders
Who would provide the final approval for decisions made for a bullying awareness program?
Project sponsor
Who would make sure the school fundraiser was organized by the spring deadline?
Project manager
Who would research and report on wellness programs used across the country?
Project team members
3 — Project Manager Roles & Responsibilities
Garrett had to build a team of teachers who would take on extra responsibilities. To gain their
support, he negotiated changes in some teachers' committee assignments and club activities.
This study source was downloaded by 100000773243632 from CourseHero.com on 03-30-2022 14:55:29 GMT -05:00
https://www.coursehero.com/file/63396285/PM375-Unit-1-Challenge-12docx/
Garrett used __________ when he negotiated with teachers and encouraged their support of
the project.
interpersonal skills
Laura always made sure to produce high-quality documents for her team so they were well
prepared.
Which key project manager skill is Laura using?
Communication skills
When Paula is coordinating the timing of activities for the school fundraiser event, she is using
_________.
organizational skills
4 — Project Life Cycle & Processes
Luke verifying that all deliverables are complete and meet requirements would occur in which of
the following phases?
Phase 4
Elizabeth determining the project's budget would occur in which of the following phases?
Phase 1
Olivia determining who will be the team members on the project would occur in which of the
following phases?
Phase 2
5 — Types of Projects
Goldman Grocery creates a training course for employees on the proper storage and use of new
bags at the store registers.
This activity would be considered a __________ project.
This study source was downloaded by 100000773243632 from CourseHero.com on 03-30-2022 14:55:29 GMT -05:00
https://www.coursehero.com/file/63396285/PM375-Unit-1-Challenge-12docx/
process
Clothing Emporium designs a website search that lets customers find store locations that dispose
of old bags for customers.
This activity would be considered a __________ project.
service
Star Records develops eco-friendly bags in two colors from which a customer can choose.
This activity would be considered a __________ project.
product
6 — Project Methodologies
Which of the following characterist