The team on which Regina and Daniel serve is responsible for quality testing before each deliverable is
released to the client. Those two own the q
...
PMP Exam Prep - Quality Questions and
Answers with Complete Solutions
The team on which Regina and Daniel serve is responsible for quality testing before each deliverable is
released to the client. Those two own the quality process for the rest of the team. They make use of
flowcharts, tree diagrams, audits, and affinity diagrams in their analysis each week. According to PMI,
what quality process are Regina and Daniel performing?
A. Plan Quality Management
B. Perform Quality Assurance
C. Control Quality
D. Perform Quality Analysis Correct Answer-B
While checking to see if the deliverables meet the stakeholders' quality specifications, the project team
discovers a common defect. After making several adjustments to the timing of an execution process,
subsequent measurements indicate that the defect is still consistently present in the resulting
deliverables. The summary report of this defect repair attempt states that:
A. The process timing adjustments and the measured defects are mutually exclusive events
B. The expected values of the defect measurements are inconsistent with the design of experiments
optimization
C. The attempted adjustments are negatively linearly correlated with the defect metrics
D. The consistent defect measurements are statistically independent from the process timing
adjustments Correct Answer-D
Tonia and Maggie are reviewing the results of the latest rounds of tests with their fellow engineers.
Their group has established standard practices that translate to specific steps to be carried out by the
implementation team. If these steps are carried out properly, the likelihood of product acceptance is
extremely high. Tonia and Maggie are flipping through the results of the tests and making note of the
dates the tests were carried out. A certain number of tests should've been completed prior to the
release - that's what they are checking. What is being described here?
A. Tonia and Maggie are performing quality assurance
B. Tonia and Maggie are using statistical sampling to ensure that proper steps are executed in the
correct sequence
C. Tonia and Maggie are making use of statistical sampling to be efficient with project spending while
ensuring that the product will be accepted
D. Tonia and Maggie are performing quality control Correct Answer-A
In a control chart, the mean is represented as a horizontal line. This is also:
A. The average of the control limits
B. The average of all data points outside the specification limits
C. The average of the Rule of Seven
D. A means of identifying assignable cause Correct Answer-A
Of the following processes in Quality Management, which process is started first?
A. Define Quality
B. Perform Quality Assurance