How does the Scrum Master provide the most value to the team?
-by facilitation discussion between the product owner and the development team
-by ensuring time b
...
Scrum Test (4.6)-4 Questions and
Answers Already Passed
How does the Scrum Master provide the most value to the team?
-by facilitation discussion between the product owner and the development team
-by ensuring time boxes are kept during team meetings and working sessions
-by scheduling scrum supported events to ensure team alignment
-by ensuring impediments are removed for the development team ✔✔-by ensuring impediments
are removed for the development team
What are two common anti-patterns during PI planning? (choose 2)
-Alignment becomes the goal, rather than a detailed plan
-pressure is put on teams to overcommit
-a detailed plan becomes the goal rather than alignment
-the team determines where change should be targeted
-the team backlog is applied to a very targeted part of the organization ✔✔-pressure is put on teams
to overcommit
-a detailed plan becomes the goal rather than alignment
which two actions are part of the scrum master's role in PI planning?
-align the value stream and agile release trains to a common vision
-serve as the customer proxy and work with product management
-manage the program board
-ensure the team builds a plan they can commit to
-prioritize features to support the program vision ✔✔-align the value stream and agile release
trains to a common vision
-ensure the team builds a plan they can commit to
what are two safe opportunities for driving relentless improvement?
-iteration retrospective
-PI planning management review and problem solving
-daily standup
-PI planning
-inspect and adapt workshop ✔✔-iteration retrospective
-inspect and adapt workshop
what is one of the scrum master's responsibilities during the IP iteration?
-update the team's PI roadmap
-create the team's PI predictability report
-remove the scope that exceeds capacity
-update capacity ✔✔-remove the scope that exceeds capacity
what is accomplished in the first part of the PI planning meeting?
-the scrum master decides how much work can be accomplished
-items are selected from the program backlog
-all tasks are defined
-the product owner defined the iteration goal ✔✔-the product owner defined the iteration goal
the scrum master role includes traditional scrum team leadership and responsibilities to which
other group?
-the the value stream engineers
-to the agile teams at the program level
- to the business owners
-to the teams that make up the lean portfolio ✔✔-to the agile teams at the program level
at the end of the first iteration the team finishes user stories A, B, and 50% of C. The story sizes
are set at these points:
Story A= 8 points
Story B= 1 point
Story C= 5 points
Story D= 3 points
What is the team's velocity?
-7
-14
-11.5
-9 ✔✔-11.5
How often should a system d