SAFe scrum master Questions and
Answers with Verified Solutions
Which two activities could a scrum master and team focus on for the first team breakout session
of PI planning?
Get business values assigned to PI objec
...
SAFe scrum master Questions and
Answers with Verified Solutions
Which two activities could a scrum master and team focus on for the first team breakout session
of PI planning?
Get business values assigned to PI objectives
Begin identifying team dependencies
Create the team's draft PI obj
Identify and document team level risks
Plan each iteration's details ✔✔Create the team's draft PI obj
Identify and document team level risks
What is one benefit of program increment objective?
They ensure accurate status reporting
They create a near-term focus and vision
They describe a process for defining team goals
They form a guiding coalition ✔✔They create a near-term focus and vision
While assigning business value, the business owner gives a value of two to a team PI objectives
that they see as more technical in nature. This concerns the team due to the critical nature of the
work. What is the best action for the Scrum master to take?
Escalate to the release train engineer and product manager
Challenge the business owner and ensure that a more higher
business value is assigned to the objective
Facilitate an opportunity for a team to explain their
perspective of the business value delivered by the objective.
Tell the team that business owners can provide any business value that they think is right.
✔✔Facilitate an opportunity for a team to explain their
perspective of the business value delivered by the objective.
What are two inputs of PI planning?
PI objectives
Team goals
Story estimates
vision
Features ✔✔Vision
Features
Cadence and synchronisation help reduce uncertainty and manage what?
Capacity allocation
Other commitments
The variability in solution development
Product management ✔✔The variability in solution development
When looking at a program board at the end of PI planning, what does it mean when a feature is
placed in a team's swim lane with no strings?
That the feature can be completed by that team independently
That the team has not broken the feature into stories yet and has not identified dependencies
That the team has been assigned, but the feature dependencies have not been identified yet
That it has dependencies on teams in other Agile release trains (ARTs) or solution trains ✔✔That
the feature can be completed by that team independently.
What is one characteristic of an Agile team's Iteration?
Are typically 8-12 weeks long
The scrum master is responsible for approving the duration
The duration can be extended to complete unfinished testing
Scope changes should be minimized once it starts ✔✔Scope changes should be minimized once it
starts.
A scrum master notices that the team mem