Question 1
What is the time duration that is consumed by the agile scrum sprint?
• 1 hour
• 1 day
• 3-4 weeks
• None
Usually, the total duration of these sprints relies on the project scale and the project team doi
...
Question 1
What is the time duration that is consumed by the agile scrum sprint?
• 1 hour
• 1 day
• 3-4 weeks
• None
Usually, the total duration of these sprints relies on the project scale and the project team doing work on
it. The completion of these sprints takes 3-4 weeks as an average. The team members are can be 3-9 in
each team for a single project.
--------------------------------------------------------------------------------------------------------------------
Question 2
What is the term “Velocity” used for in scrum?
• Print by sprint progress rate of a team
• The speed of project execution
• The average capacity of team members
• None of the above
The term velocity never can be compared regarding two different teams. Generally, it is usually used for
understanding if some real projects are being done by the project team.
---------------------------------------------------------------------------------------------------------------------
Question 3
In the scrum, what is the term “impediments” is about?
• An issue that block the scrum team in project completion
• Project speed boosters
• External resources to help the project
• Information resources
The term impediments are basically some problems and issues that put a stop to the project team and
their work. The impediments can occur in any kind of object and they cause a problem in project
completion.
------------------------------------------------------------------------------------------------------------------
Question 4
Which one of the options is the main difference between scrum and agile?
• Agile is a procedure whereas scrum is practice
• Scrum is a procedure and agile is a practice
• Scrum is a large spectrum whereas agile is the form of scrum itself
• Scrum is incremental and agile is not
The agile is a large entity and scrum is just a small part of it. Both these concepts are iterative in terms of
their nature and working. The main difference is that agile is a whole methodology whereas the scrum is
just a little practice involved within agile