The contract documents for a project should be written primarily to protect the interest of the
CM. - ✔✔False
The owner, CM and Designer are less likely to be involved in disputes with the
...
CMIT Test Practice Questions
The contract documents for a project should be written primarily to protect the interest of the
CM. - ✔✔False
The owner, CM and Designer are less likely to be involved in disputes with the Contractor if a
contract is awarded to the lowest bidder. - ✔✔False
Use of standard forms of agreement will always result in fewer disputes? - ✔✔False
After the owner accepts a cm's proposed GMP as contemplated by the CMAA CM at Risk Series
documents, the responsibilities and duties of the CM are essentially the same as if the Owner and
CM were using the AIA GMP documents. - ✔✔False
In the CMAA CM at Risk series documents, the CM may perform part of the work if the CM so
chooses? - ✔✔False
Contractors generally believe the Designer acts independently and in the joint interests of the
Owner and Contractor when making decisions regarding contract claims and change orders. -
✔✔False
The CMAA standard forms of agreements(Agency- or CM at risk series) are the best documents
for an Owner to use on all design and construction projects. - ✔✔False
The CMAA contract documents were written primarily to protect the interest of the CM. -
✔✔False
In the CMAA Agency series the Designer is entitled to object to provisions of Construction
Management Plan as prepared by the CM. - ✔✔True
When providing services specified in CMAA document A-1, the CM may have a fiscal liability
for negligent preparation of the cost estimates. - ✔✔True
In the CMAA CM at Risk Series documents, the CM is the Owner's principle agent until a GMP
is accepted by the Owner. - ✔✔True
If an Owner uses the CMAA documents A-4, the Owner may be obligated to compensate the
Designer as an additional service for site visits requested by the CM. - ✔✔True
If a Designer uses the CMAA A-4 contract document instead of the AIA B-141/CM document,
the Designer's exposure to professional liability during the construction phase is reduced. -
✔✔True
The CM has the autority on behalf of the owner to disapprove or reject work and to revoke, alter,
enlarge or relax and requirements of the contract documents. - ✔✔False
The Owner has the obligation to exercise its right to stop work when it would be to the benefit of
the Contractor and the Contractor requests the Owner to exercise that right. - ✔✔False
All communications to the Designer and Owner from the Contractor must be submitted through
the CM - ✔✔True
The Owner shall pay all charges to utility owners for any of the connections to the work. -
✔✔False
The Contractor has no obligation to provid