CFCM Final Exam Questions
What is a Certificate of Competency? - ✔✔A certificate issued by the SBA stating that the
holder is responsible, for the purpose of receiving and performing a specific Government
contract
Ex
...
CFCM Final Exam Questions
What is a Certificate of Competency? - ✔✔A certificate issued by the SBA stating that the
holder is responsible, for the purpose of receiving and performing a specific Government
contract
Except as specifically permitted by executive agencies, the fast payment procedure may not be
used for individual purchasing instruments exceeding what amount? - ✔✔$35,000
What can a contractor access online at www.fedbizopps.gov? - ✔✔The government wide point
of entry
Application of size standards includes specifying the size standard in the - ✔✔solicitation
When the value of the contract is $100,000 the agency will be required to use - ✔✔SAP
How is the publication of a paid advertisement in a newspaper authorized? - ✔✔By the head of
the agency, by giving written authorization
The unilateral right in a contract by which the Government may elect to purchase additional
supplies or services called for by the contract is called what? - ✔✔Option
If a prospective contractor is qualified and eligible to receive an award, but lacks adequate
financial resources to perform the contract, can the contractor be determined responsible? - ✔✔If
the contractor presents evidence of the ability to obtain adequate financial resources, the
contractor may be determined responsible
What are methods for simplified acquisition? - ✔✔Blanket purchase agreement,
Governmentwide commerica lpurchase card, Purchase Order
For a contract exceeding the simplified acquisition threshold, an offeror (other than an
individual) that does not agree to provide a drug-free workplace is what? - ✔✔Not considered a
responsible source
What law specifies how agencies shall make their records available upon public request, imposes
strict time standards for agency responses, and exempts certain records from public disclosure? -
✔✔Freedom of Information Act
Who is responsible for printing, publishing, and distributing the Federal Acquisition Regulation?
- ✔✔The FAR Secretariat, as authorized by GSA
Which FAR Part prescribes policies and procedures unique to the acquisition of commercial
items? - ✔✔FAR Part 12
Which of the following is necessarily true about a cost that is assignable or chargeable to one or
most cost objectives on the basis of relative benefits received or other equitable relationship? -
✔✔The cost is allocable
A mineral required for production in performance of a contract is not mined in the United States,
but can be acquired from another country. How does the Buy American statute apply in this
case? - ✔✔The mineral may be acquired from a foreign source if it is in the best interest of the
Government
When it is in the best interest of the Government to consider award to other than the highest
technically rated offeror, which of the following should the Government use to select the source?
- ✔✔A tradeoff process
The obtaining of opinions, special knowledge, or skills from noted experts would be included in
what kind of service? - ✔✔Advisory and assistance service
Who is authorized to execute contract modifications on behalf of the Government? - ✔✔Only a
contracting officer acting within the scope of his or her authority
Which FAR part prescribes policies and procedures for contracting for supplies and services
under the Federal Supply Schedule program? - ✔✔Part 38
If hazardous materials are expected to be used during contract performance, what must the
apparent successful offeror do prior to contract award? - ✔✔Furnish hazardous material data on
a Material Safety Data Sheet
A failure in estimating, accumulating, or reporting costs to comply with applicable cost
accounting standards is called what? - ✔✔Noncompliance
Who is authorized to sign a contract on behalf of the United States? - ✔✔Only the contracting
officer
A cash fund of fixed amount established by an advance of funds, for disbursement in cash for
relatively small amounts is called what? - ✔✔Imprest fund
The Government's policy is to try to resolve all contractual issues in controversy by what? -
✔✔Mutual agreement at the contracting officer's level
What are examples for justification of emergency acquisitions flexibilities? - ✔✔The President
has issued a major disaster declaration, The acquisition is to facilitate the defense against a
nuclear attack against the United States, The acquisition is in support of a contingency operation
What is a function that must be delegated to a CAO if the agency has not designated the CO to
perform it? - ✔✔Negotiation of forward pricing rate agreements
Which of the following is not an example of information technology? Software development, A
computer hard drive, building's digital thermostat, or modem - ✔✔digital thermostat
When shall certified cost or pricing data be obtained? - ✔✔negotiated procurement is expected
to exceed $750,000
What technique promote the early exchange of information with industry? - ✔✔Market research
When evaluating a proposal, what rating method is an agency required to use to assess the
evaluation factors specified in the solicitation? - ✔✔agency may use any method or combination
of methods
Standard Form 44 is also known as what? - ✔✔Purchase Order—Invoice—Voucher
Under FAR Part 5, contract actions must be synopsized in the GPE if they exceed what amount?
- ✔✔$25,000
In which FAR Part is the Uniform Contract Format outlined? - ✔✔Part 15
What is required when a change order is not forward priced? - ✔✔Documentation of the change
order and an agreement to an equitable adjustment in contract terms
A contractor infringes on a copyright with the authorization of the Government. What remedy is
available to the copyright holder? - ✔✔A suit for monetary damages against the Government in
the Court of Federal Claims
In the FAR citation "FAR 25.1102(a)(2)," what is referred to by the number 11? - ✔✔Subpart
25.11
Which of the following contract types is generally used to acquire construction? - ✔✔Firmfixed-price
Which of the following would be necessary for sealed bidding to be appropriate? - ✔✔The
award will be made on the basis of price and price-related factors
Which of the following is true about acquisitions for which the World Trade Organization
Government Procurement Agreement applies? - ✔✔The contracting officer must not include
technical requirements in solicitations solely to preclude the acquisition of eligible products
Who is generally responsible for granting approval of a contractor's purchasing system? -
✔✔administrative contracting officer
The process of establishing a reasonable amount to be paid for supplies or services is called
what? - ✔✔Pricing
What is the term for the amount of money specified in a bond as the maximum payment for
which the surety is obligated? - ✔✔Penal amount
Which of the following is a true statement about the role of the Acquisition Team? - ✔✔The
procurement policies and procedures that are used by members of the Acquisition Team are
outlined in the FAR
When is consent to subcontract generally required? - ✔✔When the contractor has an approved
purchasing system
When will the acquisition procedures of FAR Part 12? - ✔✔Performance-based acquisition,
Acquisition of a commercial-off-the-shelf item, Acquisition based on the results of market
research
What methods of contract financing is least preferred by the Government? - ✔✔Advance
payment
Which of the following is the Government permitted to do after receipt of proposals? - ✔✔Make
an award without holding discussions, if the solicitation says this is intended
Which of the following public relations or advertising costs would be unallowable? Hosting a
ceremony to announce a new product, Participating in community service activities, Providing a
tour or open house of a facility, Responding to inquiries on company policies - ✔✔Hosting a
ceremony to announce a new product
A contract that is awarded using other than sealed bidding procedures is what? - ✔✔A
negotiated contract
Generally, when shall acquisitions of supplies or services be automatically reserved exclusively
for small business concerns and set aside for small businesses? - ✔✔When the anticipated dollar
value exceeds $3,500 but does not exceed $150,000
What is the minimum amount of information that a request for proposals for competitive
acquisitions shall contain? - ✔✔The government's requirement, the anticipated terms and
conditions that will apply to the contract, the information required to be in the offeror's proposal,
and factors that will be used to evaluate the proposal
When is posting an RFQ on e-Buy required? - ✔✔When the order contains brand-name
specifications
In an acquisition plan, which of the following is a responsibility of the agency head (or the
agency head's designee)? - ✔✔Promoting and providing for full and open competition
For agencies delegated authority to establish new Federal Supply Schedules, what must the
contracting officer do prior to establishing such a contract? - ✔✔Obtain approval from the GSA
Federal Supply Service
A contract for demolition of a public building, without any further construction work, is subject
to which of the following? - ✔✔Only the Service Contract Labor Standards statute
What is the difference between a personal services contract and a nonpersonal services contract?
- ✔✔Under a personal services contract, the personnel rendering the services appear to be
subject to government supervision and control
A legal instrument in which a contractor guarantees performance of the contract, the obligations
under the contract are assumed by a successor in interest, and the government recognizes the
transfer of the contract and related assets is called what? - ✔✔Novation agreement
Which of the following contract types would be most appropriate for acquisition of a commercial
item if the contract was not awarded using competitive procedures? - ✔✔Firm-fixed-price
When requesting information from potential sources in market research, what should agencies
do? - ✔✔Request the minimum amount of information necessary
Except for copyrighted works, what rights does the Government acquire in data first produced in
the performance of a contract? - ✔✔Unlimited rights
What is a CPSR and what is its purpose? - ✔✔Contractor Purchasing System Review; to
evaluate the efficiency and effectiveness with which the contractor spends Government funds
Which of the following is not a function of the General Services Administration? Authorizing
other agencies to award schedule contracts, Management of U.S. Federal property, Managing
schedule contracting for military items, Publicizing regulations governing acquisition of real
property - ✔✔Managing schedule contracting for military items
What is the purpose of first article testing and approval? - ✔✔To ensure that a contractor can
furnish a product that conforms to all contract requirements for acceptance
For research and development work performed under a cost-plus-fixed-fee contract, what is the
maximum fee that may be negotiated? - ✔✔The contracting officer shall not negotiate a price or
fee that exceeds the following statutory limitations]) For experimental, developmental, or
research work performed under a cost-plus-fixed-fee contract, the fee shall not exceed 15 percent
of the contract's estimated cost, excluding fee
Which of the following is true about the priority of DPAS-rated orders? - ✔✔All DO rated
orders have equal priority with each other and take preference over unrated orders. All DX rated
orders have equal priority with each other and take preference over DO rated and unrated orders
Which of the following is true about postaward notifications to offerors whose proposals were
not selected for award? - ✔✔The notice must be provided within three days of contract award,
and shall not contain the cost breakdown of any other offeror
To the maximum extent practicable, FAR Part 37 requires the use of what for acquisitions of
services? - ✔✔Performance-based acquisition
When should the contracting officer charge interest on the balance of an advance payment? -
✔✔For all contracts, except when interest is excluded by statute or agency procedures
When a make-or-buy program is required of a contractor, how should major items be
categorized? - ✔✔"Must make," "must buy," or "can either make or buy"
If The offeror is the firm that designed the project - ✔✔construction of a project not be awarded
A contractor receives a refund relating to an allowable cost. What shall the contractor do with the
applicable portion of the refund? - ✔✔The contractor may credit it to the Government either as a
cost reduction or a cash refund
Drawings submitted by a contractor to show the construction of a particular structure as actually
completed under the contract are called what? - ✔✔Record drawings
At the lowest level, who is directly responsible for reviewing an agency's contracting operations
and identifying and reporting opportunities and actions taken to acquire commercial items to
meet its needs? - ✔✔Agency advocate for competition
Which of the following terms means a list of products that have been examined and tested, and
have satisfied all applicable requirements? - ✔✔Qualified products list
A contractor transfers its right to be paid by the Government for contract performance to a trust
company. What is this called? - ✔✔Assignment of claims
Which of the following is an inherently governmental function? - ✔✔Interviewing applicants for
Federal employment
What is buying-in? - ✔✔Submitting an offer below anticipated costs, expecting to increase the
contract amount after award or to receive follow-on contracts at higher prices
What are reasons to use a liquidated damages clause in a solicitation? - ✔✔The extent of the
damage expected by the Government cannot be accurately estimated, Timely performance is so
important that the Government will suffer damage if performance is delinquent, The Government
may reasonably expect to suffer damage if the delivery is delinquent
A contractor has made an invention under a Federal research and development contract. In which
of the following cases may the contractor be required to assign title to the invention to the
Government? - ✔✔A contract may require the contractor to assign to the Government title to any
subject invention w]hen the contractor is not located in the United States or does not have a place
of business located in the United States or is subject to the control of a foreign government"
Except as authorized by law, what is the maximum term of contracts for services that are funded
by annual appropriations? - ✔✔Until the end of the fiscal year of the appropriation
If market research indicates that commercial or nondevelopmental items might not be available
to satisfy agency needs, what shall the agency do? - ✔✔Reevaluate the need and determine
whether the need can be restated to permit commercial or nondevelopmental items to satisfy the
agency's need
In which of the following cases may a time-and-materials contract be used? - ✔✔When it is not
possible at the time of placing the contract to estimate the extent of the work
To the maximum extent practicable, all contracts for the acquisition of commercial items shall
include which clauses? - ✔✔Only those required to implement laws applicable to the acquisition
of commercial items, or those determined to be consistent with customary commercial practice
What is a required element in a Broad Agency Announcement? - ✔✔description of the agency's
research interest, The criteria by which proposals will be selected, and The period of time during
which proposals will be accepted
When can an agency consider an unsolicited proposal on a sole source basis? - ✔✔proposal is
for research, and justification and approval have been obtained
Which FAR part specifies the definitions for words and terms that are to be used unless another
FAR part provides a different definition for that part? - ✔✔Part 2
If the information collected is still current, accurate, and relevant, a contracting officer may use
market research conducted up to how long before the award of a task or delivery order? - ✔✔18
months
Which of the following contract types provides a base fee plus an additional amount which is
based on a judgmental evaluation by the Government of the quality of contract performance? -
✔✔Cost-plus-award fee
What is the preferred method of transporting supplies for the Government? - ✔✔Commercial
carriers
What is GSA Standard Form 30 (SF30)? - ✔✔Amendment of Solicitation/Modification of
Contract
A contractor under a construction contract provides the Government with a quantity of unitpriced items other than the quantity called for. Can the Government or the contractor demand an
adjustment in the contract price? - ✔✔Yes, if the variation exceeds plus or minus 15 percent of
the expected quantity
What is the order of precedence among the 8(a) Program, HUBZone Program, Service-Disabled
Veteran-Owned Small Business Procurement Program, and Women-Owned Small Business
Program? - ✔✔There is no order of precedence
Which of the following contract modifications needs to be signed by both the contractor and the
contracting officer? - ✔✔An agreement definitizing a letter contract
Which contract type places maximum risk and full responsibility for all costs and resulting profit
or loss on the contractor? - ✔✔Firm-fixed-price
Which of the following is a true statement about suspension and debarment? - ✔✔Debarment
excludes a contractor from government contracting for a specified period, and suspension
temporarily disqualifies a contractor from government contracting.
Debarment is not permanent - ✔✔
What law governs the collection, maintenance, use, and dissemination of personally identifiable
information about individuals that is maintained in systems of records by federal agencies? -
✔✔Privacy Act of 1974
What is an example of an exemption to a member of the public under the Freedom of
Information Act? - ✔✔A statement made by a contracting officer to a mediator to resolve a
dispute
A contractor's arrangement to pay contingent fees for soliciting or obtaining Government
contracts is considered contrary to public policy. Which of the following statements explains
why? - ✔✔Such arrangements may lead to attempted or actual exercise of improper influence
What is a Certificate of Competency? - ✔✔A Certificate of Competency (COC) is the certificate
issued by the Small Business Administration (SBA) stating that the holder is responsible ... for
the purpose of receiving and performing a specific Government contract."
Except as specifically permitted by executive agencies, the fast payment procedure may not be
used for individual purchasing instruments exceeding what amount? - ✔✔$35,000
Which of the following contract types allows for disallowing costs during the course of
performance, after the costs have been incurred? - ✔✔"Cost-reimbursement contracts, the costreimbursement portion of fixed-price contracts, letter contracts that provide for reimbursement of
costs, and time-and-material and labor-hour contracts provide for disallowing costs during the
course of performance after the costs have been incurred."
What is a CPSR and what is its purpose? - ✔✔The objective of a contractor purchasing system
review (CPSR) is to evaluate the efficiency and effectiveness with which the contractor spends
Government funds and complies with Government policy when subcontracting."
Which of the following is true about acquisitions for which the World Trade Organization
Government Procurement Agreement applies? - ✔✔The contracting officer must not include
technical requirements in solicitations solely to preclude the acquisition of eligible products