57101-11 Introduction to Solar Photovoltaics
The average solar irradiance is _______. - ✔✔1,000 W/m2
The organization that certifies PV installers is _______. - ✔✔NABCEP
The default azimuth angle for locations in the
...
57101-11 Introduction to Solar Photovoltaics
The average solar irradiance is _______. - ✔✔1,000 W/m2
The organization that certifies PV installers is _______. - ✔✔NABCEP
The default azimuth angle for locations in the northern hemisphere is _______. - ✔✔180 degrees
A PV cell is a type of ______. - ✔✔A semiconductor
What is the voltage when the current is 20A and the resistance is 12 ohms? - ✔✔240 volts
Which of the following is an example of a direct-drive standalone system? - ✔✔A DC-powered
irrigation system
Which of the following is true regarding a grid-interactive system? - ✔✔It provides power when
there is a grid outage.
What is the resistance when the voltage is 120V and the amperage is 5A? - ✔✔24 ohms
Which of the following is true regarding parallel circuits? - ✔✔A parallel circuit provides
multiple paths for current flow.
What is the power when the current is 20A and the voltage is 120V? - ✔✔2,400 watts
Wiring solar panels in series _____. - ✔✔increases the voltage but does not affect the amperage.
Wiring two 20v/5A solar panels in parallel produces _____. - ✔✔20V/10A
Which of the following months would be likely to have the lowest insolation values? -
✔✔December
The peak sun hours for a site receiving 1,000 W/m2 for three hours and 900 W/m2 for five hours
is ______. - ✔✔7.5 hours
Which of the following is typically considered a BOS component? - ✔✔Wiring
What is the panel operating temperature under Standard Test Conditions? - ✔✔25*C (77*F)
Which of the following statements is true regarding PV power? - ✔✔PV systems help to offset
power use during peak demand periods.
Which of the following PV cells is likely to have the highest efficiency? - ✔✔Monocrystalline
Which of the following is often the result of repeated temperature cycling? - ✔✔Burnt terminals
Which of the following covers specific PV system components? - ✔✔UL Standard 1703
Each battery cell produces ______. - ✔✔2V
A 80 Ah battery from which 40 Ah has been withdrawn has undergone a DOD of _____. -
✔✔50%
Per NEC Section 690.71(B)(1), residential PV batteries connected in series are limited to
________. - ✔✔48V
What is the effect of temperature on irradiance? - ✔✔The irradiance decreases by 50% for every
ten-degree temperature increase.
The best charge controller for use with sealed batteries is a ______. - ✔✔PWM charge controller
Strings of solar panels are likely to be connected in a(n) _______. - ✔✔combiner box
The most labor-intensive portion of a ground-mounted installation is typically the _____. -
✔✔support system installation
The current electrical loads are determined during the _______. - ✔✔customer interview
Straight ladders must be positioned ______. - ✔✔so that they extend beyond the roof surface by
at least 36 inches
The equipment manufacturing standards for PFAS systems are covered by ______. - ✔✔ANSI
The fasteners installed in a PV system must _______. - ✔✔be torqued to the manufacturer's
specifications
A battery should be replaced ______. - ✔✔if it appears swollen
The type of inverter best suited to sensitive electronic applications is a ________. - ✔✔true sine
wave inverter
The required free length between a worker and any hazard or obstruction when using a new 12-
foot lanyard is______. - ✔✔20'
Wind loads can be minimized by mounting arrays no closer than ______. - ✔✔3' from the edge
of the roof
The primary design consideration from the customer's perspective is almost likely the _______. -
✔✔cost
For maximum power output in summer in the northern hemisphere, the tilt angle should equal
______. - ✔✔local latitude - 15 degrees
Which of the following components must be protected against temperature extremes? -
✔✔Batteries
Which of the following cable types is most likely to be used with a PV array? - ✔✔USE-2
Suppose a customer lives in an area with five peak sun hours per day, uses an average of 25 kWh
per day during the critical design month, and desires 50% replacement of grid power. What is the
required system size? - ✔✔2,500 Wh/day
Inverter sizing is based on ______. - ✔✔the total wattage of all loads expected to operate at one
time
A loose or corroded system connection can be found by performing a(n) _______. - ✔✔selective
shading test
Suppose you have a 24 VDC nominal battery that is supplying a 5a, 120 VAC load with a duty
cycle of 5 hours per day. What is the true battery load? - ✔✔125 Ah
The roof ground should be a minimum of ______. - ✔✔6 AWG
What is the voltage correction factor for a system with a winter design temperature of -10*F? -
✔✔1.20
The largest system that can be installed on 300 square foot of roof area using panels rated at 15W
per square foot is ______. - ✔✔4.5 kWh
Suppose a PV panel has a VOC of 20V, six panels will be connected in series, and the voltage
correction factor for the location is 1.20. What is the system output voltage? - ✔✔144V
Which of the following locations for a roof array is likely to experience the most drag? -
✔✔Syracuse, New York