AFSB 152 Practice Exam Part A
The two main types of construction are heavy and highway construction and - ✔✔The general
building trades
Dramatic increase in project size, taking work in new geographical areas, moving
...
AFSB 152 Practice Exam Part A
The two main types of construction are heavy and highway construction and - ✔✔The general
building trades
Dramatic increase in project size, taking work in new geographical areas, moving into new types
of construction, and lack of management maturity are all factors that can result in -
✔✔Contractor failure
The Miller Act requires a contractor on a federal construction project to post two bonds, a
performance bond and a - ✔✔Labor and material payment bond
Contractors would typically be granted relief from bidding mistakes from errors in -
✔✔Mathematical calculation
Profitable construction can be achieved by careful estimating, good construction practices, and -
✔✔Efficient job supervision
Most sureties use the 10 percent rule when underwriting bonds. An explanation from the
contractor is required when - ✔✔There is a 10 percent or greater difference between the first and
second bids.
A contractor might finance or refinance equipment or real estate. This financing, secured by real
estate and payable in monthly installments over five to fifteen years, is called - ✔✔A term loan
Which one of the following types of financial statements do sureties prefer with a bond
application? - ✔✔Audit
The primary consideration that influences most contractors in electing a tax reporting method is -
✔✔The deferral of income tax payments to the greatest extent
possible.
The analyst's notes taken during the review of the contract status report might include all of the
following, EXCEPT: - ✔✔Gross profit (loss) recognition
A financial analyst might check for a management change such as that associated with a
stockholder's death, retirement, resignation, or termination when signaled by - ✔✔A treasury
stock transaction
From the analyst's viewpoint, accumulated depreciation or amortization on fixed assets
represents - ✔✔A calculated reduction of value from the cost or capitalized
basis of the assets.
The income statement line-item that is widely recognized as the best measure of the contractor's
success in the principal business activity is - ✔✔Income from operations.
One of the principal areas included in a forecast of financial
conditions and financial results is - ✔✔Expected financial performance of construction contracts
and
backlogs.
An essential step for trend analysis and forecasting is - ✔✔Formulate an overall judgment of
financial trends.
Supply contracts that surety underwriters do not consider hazardous involve products that are
easily replicated, can be purchased from a variety of sources, and - ✔✔Are short in duration
A claim representative needs the principal's cooperation when
gathering information to process a claim. One problem that could result from an uncooperative
principal is - ✔✔Payment of additional attorneys' fees and expenses to enforce
the surety's rights.
A surety claim representative has many sources of information available. However, the logical
starting point for the claim representative is the - ✔✔Surety's underwriters and their tiles.
The two main sources of construction work in the United States are the federal, state, and local
governme1lts and - ✔✔Private business and industry.
In starting the design process, the design professional interviews the client and measures current
and future needs and reviews existing facilities for potential renovation and ability to handle
future growth needs. What is the next step? - ✔✔Professional engineers, architects, and attorneys
obtain
required zoning approvals and ensure that plans and
specifications comply with all government regulations.
All of the following are primary functions in a successful construction firm, EXCEPT: -
✔✔Management development
John, a general contractor, produces good cash flow through frontloading. Typically, all of the
following statements are true, EXCEPT: - ✔✔Frontloading would increase John's cash flow in
the later
stages of the project.
The owner of a project does not pay Chip Construction in a timely fashion and Chip's cash flow
is disrupted. Other than frontloading other jobs, how would Chip manage immediate cash flow
problems? - ✔✔Obtain a bank credit line
Types of construction contracts are distinguished by examining the wording in the - ✔✔Payment
clause.
The traditional alternative available to a contractor who cannot settle its dispute with the owner
through arbitration procedures is - ✔✔Litigation.
The party responsible for the adequacy of the design or the efficiency of the building or system is
the - ✔✔Architect or engineer.
Overhead costs include all of the following indirect costs necessary to support the actual
construction, EXCEPT: - ✔✔Labor
Contractors subcontract various portions of the construction work to achieve the benefit of -
✔✔Specialization.
The bond penalty, or limit 6f liability, for most bidbonds is expressed as - ✔✔A percentage of
the contractor's bid.
A producer's responsibilities include knowing the bond markets, advising the contractor, keeping
the underwriter informed, reviewing underwriter decisions, appealing decisions, and -
✔✔Supporting decisions
The term "underwriting submission" could be used to describe - ✔✔An annual updating of the
file on an established. account.
All of the following are challenges to underwriting bonds for newly formed companies,
EXCEPT: - ✔✔Geographic location
Factors that influence the quality and usefulness of a contractor's financial statement are ( 1)
scope of engagement of the CPA or preparer, (2) completeness of the financial statement, (3)
accounting methodology and methods used to measure the contractor's financial condition, and (
4) - ✔✔Qualifications of the CPA or preparer.
The Schedule of Changes in Long-Term Liabilities - ✔✔Shows the effects of borrowing,
payment, or reclassification
of debt.
Which one of the following methods of construction accounting does not realistically measure
financial performance of work actually performed during the accounting period, except for
contracts that were started and completed during that period? - ✔✔Completed-contract method
Status reports help assess financial stability by - ✔✔Comparing estimates of original gross
profits with subsequent
estimates.
What is another term used to describe "billings in excess of costs and recognized earnings"? -
✔✔Overbillings
Backlog is a critical underwriting factor because the limits to which the contractor and surety
agree generally define a contractor's - ✔✔Bonding capacity.
One factor affecting the analyst's ability to make a realistic assessment of financial data is -
✔✔Access to the contractor's CPA or personnel with data or
insights.
All of the following events or changes occurring after statement preparation might affect a
financial analysis either positively or negatively, EXCEPT: - ✔✔Litigation involving the CPA
could create uncertainty.
A part of the financial statement that provides the analyst further insight into business activity
and liquidity other than the amount of working capital and that reveals the effects of the
contractor's operating, investing, and financing activities is the - ✔✔Statement of cash flows.
All of the following are miscellaneous accrued expenses, EXCEPT: - ✔✔Accounts payable
When comparing the immediacy of estimates due subcontractors and retainages due
subcontractors, which one of the following is true? - ✔✔Earned estimates due subcontractors are
among the most immediate debt obligations.
Which one of the following is the income statement line item widely recognized as the best
measure of the contractor's overall financial performance and the "bottom line" result? - ✔✔Net
income
The most important objective of a complete financial analysis is - ✔✔To objectively forecast the
contractor's financial condition
and financial results.
All of the following are principal financial areas subject to trend analysis, EXCEPT: - ✔✔Gross
profit comparison spreadsheets
All aspects of the contractor's finances, including trends and forecasts, current financial
condition, and recent results attained, are described as - ✔✔Capital.
The backlog to working capital ratio generally preferred by sureties is in the range of - ✔✔10:1
to 20:1.
A bond underwriter is evaluating Eagle Construction for payment and performance bonds.
Which one of the following would the bond underwriter consider the best indicator for a positive
financial forecast? - ✔✔Eagle Construction's working capital is 8 percent of
the backlog.
Which one of the following specialty contract bonds would the surety typically consider the least
hazardous? - ✔✔Supply bond
When a lender requests that it be named in the performance bond as a dual obligee with the
owner, the surety can limit its exposure by using - ✔✔A savings clause.
A turnkey contract differs from that of a conventional construction job because - ✔✔The
contractor supervises the work.
All of the following are factors that tnake trash removal contracts more complex than food
service contracts, EXCEPT: - ✔✔The "renew option clause" in most trash removal contracts
poses risk to the surety because the option is mutual.
Bennigan Builders will construct a plant as a turnkey project. The plant, owned by National
Company, will manufacture the next generation of rocket propellants for NASA National
Company requests an efficiency guarantee for certain components of the processing equipment.
All of the following are true, EXCEPT: - ✔✔National Company would request competitive bids
The principal for whom the bonds are written must indemnify the surety for any loss incurred.
This protection - ✔✔Is an implied obligation at law.
A principal requests financial assistance from its surety in response to - ✔✔A cash flow or
solvency problem
Claim representatives should determine who drafted the bond form(s) because - ✔✔Ambiguities
in contracts are interpreted against its drafter.
A surety claim representative determines various information on a performance and payment
bond claim against the prime contractor, including tl1e fact that the job's completion will be
delayed about three months resulting in a penalty for each day delayed. Which one of the
following statements is the least reliable? - ✔✔The prime contractor will incur an additional
$100,000 in
direct expenses to complete the job.
Four events that must generally occur before the surety has an
obligation to act and to respond to a claim under its performance bond are: (1) the principal must
be in default, ( 2) the obligee must declare the principal to be in default under the contract, (3)
the obligee must have performed its obligations under the contract, and ( 4) - ✔✔The obligee
must terminate the principal's right to proceed
under the contract.
When the obligee makes claim against the performance bond, the surety's least favorite option is
- ✔✔Takeover.
Key elements in a tender option are that the surety arranges for completion of the work and the -
✔✔Completion contractor provides the obligee with new bonds
Plumbing-Materials Supplier furnished pipe and fittings to a first-tier subcontractor on a federal
job. On March 1, 2003, Plumbing-Materials Supplier filed written notice to the prime contractor
that payment had not been received for materials delivered to the job site between June 23, 2002,
and July 2, 2002. Plumbing-Materials Supplier also filed a claim against the prime contractor's
payment bond, stating that Plumbing-Materials Supplier - ✔✔Has met the time to sue
requirement but has not met the
notice requirement of the Miller Act.
Which one of the following would generally be covered under the Miller Act? - ✔✔Steel and
concrete incorporated in the construction project
[Show More]