Using the Standard Capability Maturity Model Integration Appraisal Method for Process Improvement
(SCAMPI), an organiza
...
ACQ 202 Module 2 Exam: Part II
Planning - Acquisition Strategy
Development, Questions. Graded A+
Using the Standard Capability Maturity Model Integration Appraisal Method for Process Improvement
(SCAMPI), an organization whose acquisition processes are well documented and standardized would be
rated at least: - ✔✔-Level 1
-Level 2
-*Level 3*
-Level 4
When selecting a software developer, which of the following should contractors possess (Select all that
apply)? - ✔✔-*Successful past performance record*
-*Domain experience in developing comparable software systems*
-Maturity level four
-*Demonstrable mature software development capability and processes*
With regard to exceptions to the full funding policy, _________ funds are budgeted as a separate
procurement line item from the related end item.
With regard to exceptions to the full funding policy, funds used to procure long lead items for a system
with the intent to provide program continuity are known as - ✔✔-Multiyear Procurement
-Incremental
-*Advance Procurement*
-Low Rate Initial Production (LRIP)
Earned value management (EVM) reports are available to help the program manager (PM) track the
contractor's cost, schedule, and performance against a Performance Measurement Baseline. - ✔✔-
*True*-False
In the Planning, Programming, Budgeting and Execution (PPBE) process, one result of the programming
activities is the __________ - ✔✔-Future Years Development Program (FYDP)
-Budget Estimate Submission (BES)
-Defense Planning Guidance (DPG)
-*Program Objectives Memorandum (POM)*
If a contractor chooses to use their own quality system, they must demonstrate compliance with the
established military standard through formal third party certification. - ✔✔-True
-*False*
The Contracting Officer's responsibilities include all of the following EXCEPT - ✔✔-Preparing the request
for proposal
-*Managing performance of the contractor on a daily basis*
-Conducting discussions with potential offerors in response to a solicitation
-Making a modification to an existing contract
A _______ is an aggregation of program elements that reflects a macro-level force mission or support
mission of DoD. - ✔✔-Future Years Defense Program (FYDP)
-Budget
-*Major Force Program (MFP)*
-Program Objectives Memorandum (POM)
If your procurement budget request did not provide for buying a whole number of useable end items,
this would be a violation of which funding policy? - ✔✔-Annual Funding
-*Full Funding*
-Incremental Funding