________ is typically not referred to as a buffer type in critical chain project management.
A. Resource buffer
B. Free buffer
C. Feeding buffer
D.
...
PMP Exam Questions & Answers, 100%
Accurate, graded A+.Verified.
________ is typically not referred to as a buffer type in critical chain project management.
A. Resource buffer
B. Free buffer
C. Feeding buffer
D. Project buffer - ✔✔-B. Free buffer
An accepted deadline for a project approaches. However, the project manager
realizes only 75% percent of the work has been completed. The project manager then
issues a change request.
What should the change request authorize?
A. Additional resources using the contingency fund
B. Escalation approval to use contingency funding
C. Team overtime to meet schedule
D. Corrective action based on causes - ✔✔-D. Corrective action based on causes
The project manager develops a process improvement plan to encourage continuous
process improvement during the life of the project.
Which of the following is a valid tool
or technique to assist the project manager to assure the success of the process
improvement plan?
A. Change control system
B. Process analysis
C. Benchmarking
D. Configuration management system - ✔✔-B. Process analysis
The project manager meets with the project team to review lessons learned from
previous projects.
In what activity is the team involved?
A. Performance management
B. Scope identification
C. Risk identification
D. Project team status meeting - ✔✔-C. Risk identification
Which should be included in a requirements management plan?
A. The document should trace requirements to project scope / WBS deliverables.
B. It should describe how requirements activities will be planned, tracked, and reported.
C. It should trace high-level requirements to more detailed requirements.
D. It should trace requirements to business needs, opportunities, goals, and objectives. - ✔✔-B. It should
describe how requirements activities will be planned, tracked, and reported.
In a traditionally drawn decision tree, a circle represents ___________.
A. a chance to which no expected monetary value can be assigned so that a likely pay-off can not be
shown.
B. a decision to which no expected monetary value can be assigned so that a likely pay-off can not be
shown.
C. a chance to which an expected monetary value may be assigned to calculate the most likely pay-off.
D. a decision to which an expected monetary value may be assigned to calculate the most likely pay-off.
- ✔✔-C. a chance to which an expected monetary value may be assigned to calculate the most likely
pay-off.
A project management team has subcontracted work to a service company. Which of the following tools
is the best choice to assure that this company will be able to meet the quality requirements of the
project?
A. Quality audit
B. Deliverable inspection
C. Fixed price contract
D. Service level agreement - ✔✔-A. Quality audit
During execution of a project which is performed for a customer on a T&M (time and material) contract
base, a new project manager is taking over the assignment.
He discovers that two members assigned to the project have charged time without performing any work
for the project customer. Upon further investigation, he determines that this occurred because there
have been no other project assignments open for these employees. The customer is unaware of these
facts.
What should the project manager do?
A. Try to find some productive work for these staff members in the project and leave them on the team.
B. The best thing is to do nothing. The customer will not realize the problem anyway.
C. Try to find a responsible person for the over-assignment who can be made accountable.
D. Take the two people off the team immediately and arrange for the refund of the excess charges to
the customer. - ✔✔-D. Take the two people off the team immediately and arrange for the refund of the
excess charges to the customer.
Your project is executed with a globally spread virtual team. The project progress has been found to be
too slow. Which measure is most likely to immediately speed up the project?
A. Technical training for all team members
B. Daily phone conferences and detailed reporting
C. A team meeting at a location convenient to all team members
D. Collocation of team members at a suitable place - ✔✔-D. Collocation of team members at a suitable
place
A project management team wants to procure some customized products which are available in
identical grade and quality from many vendors. What should be included in the procurement package to
ensure that their offers will be comparable?
A. A statement of work describing the needs of the project in sufficient detail to enable vendors to make
suitable proposals
B. A statement of work specifying attributes and metrics of the requested deliverables in detail to allow
vendors submission of bids
C. The approved project scope statement, the WBS which should be broken down to work package level
and the WBS dictionary
D. The risk management plan and the reports from those risk management reviews which have been
made so far - ✔✔-B. A statement of work specifying attributes and metrics of the requested deliverables
in detail to allow vendors submission of bids
Which of the following becomes increasingly important in a virtual team environment?
A. Requirements engineering
B. Communication planning
C. Formal procurements closure
D. Network diagramming - ✔✔-B. Communication planning
You are assigned as the project manager to a project which is executed for a customer under FP
contract. Your customer informed you this morning that they insist on certain "refinements" of the
project scope.
You agree that the requested actions make really sense to the project, but believe that they constitute a
major change increasing the project scope. What should you do next?
A. Accept the request of the customer. Diligently document the additional costs and working hours
spent by yourself and the team on the implementation of the change and invoice these to the customer
at appropriate rates.
B. Perform earned value analysis to assess the current status of the project and get all the numbers you
need to communicate the case to the change control board which then will have to make the best
decision regarding the customer request.
C. Check the contract, the project charter, the scope statement and other documents related to the
project and the contract. Implement ADR (alternative dispute resolution) procedures if the conflict
cannot be resolved otherwise.
D. Talk to the project sales department and find a joint solution with them how to best reject the
request considering the commercial and strategic value of the customer to the organization you are
working for. - ✔✔-C. Check the contract, the project charter, the scope statement and other documents
related to the project and the contract. Implement ADR (alternative dispute resolution) procedures if
the conflict cannot be resolved otherwise.
A prime contractor in a customer project under CPFF contract has run into unexpected technical
problems. Fixing them will require a lot of additional work to be done.
The company made a decision to book more staff and equipment from their subcontractors in order to
adhere to the agreed timeline. The customer agreed to this decision.
What will most likely happen?
A. The contractor's indirect costs will increase and the customer's payment for them will increase, too.
B. The contractor's indirect costs will increase, but the customer's payment for them will not increase.
C. The contractor's indirect costs will not increase, but the customer's payment for them will.
D. Both the contractor's indirect costs and the customer's payment for them will not increase. - ✔✔-D.
Both the contractor's indirect costs and the customer's payment for them will not increase.
A project management team is evaluating the causes that might contribute to unsatisfactory
performance and quality.
Which of the following statements is not true?
A. Normal process variation is attributable to random causes and sometimes also called "white noise".
B. Special causes are easier to predict and handle than random causes (also called common causes).
C. Special causes are unusual events which are difficult to foresee and often produce outliers.
D. A process can be optimized to limit the bandwidth of variations due to random causes. - ✔✔-B.
Special causes are easier to predict and handle than random causes (also called common causes).
You are performing a project management audit in your company and find that most of the project
plans are neither consistent nor up-to-date.
Which of the following statements is not true?
A. Projects should never be executed without a valid, updated and working project management plan.
B. The consistency of the project management plan is secondary because it is only the results that
matter.
C. A great deal of effort is required to develop and update a project plan, but the benefits include less
pressure on all stakeholders and a resulting product that will satisfy the requirements.
D. Poor planning and insufficient updating of project management plans are common reasons for cost
and time overruns. - ✔✔-B. The consistency of the project management plan is secondary because it is
only the results that matter.
You want to perform active risk acceptance. What should you do?
A. Create contingency reserves in resources, money and time.
B. Develop a plan to minimize impact in case that an identified risk occurs.
C. Develop a plan to minimize the probability of occurrence for identified risks.
D. Make additional resources available to speed up the project. - ✔✔-A. Create contingency reserves in
resources, money and time.
When do bidder conferences normally take place?
A. After the contract has been awarded to keep alternatives open.
B. After submission of bid or proposal, but before contract award.
C. Prior to the submission of a bid or proposal by the bidder.
D. After technical meetings with bidders to discuss contract requirements. - ✔✔-C. Prior to the
submission of a bid or proposal by the bidder.
What is defined by control limits?
A. A measuring instrument solely used to describe process capability. The process is found capable if the
±3 sigma range is exceeded by not more than 0.3% of a tested sample lot.
B. The limits of the six sigma area on either side of a control chart to plot measured values; data found
outside the area are out of specification and can lead to rejection of an entire batch.
C. The area consisting of typically three standard deviations on either side of a mean value of a control
chart to plot measured values found in statistical quality control
D. The area consisting of typically three standard deviations on either side of a mean value of a control
chart to plot measured values found in quality assurance - ✔✔-C. The area consisting of typically three
standard deviations on either side of a mean value of a control chart to plot measured values found in
statistical quality control
The scope baseline consists of what?
A. Scope statement, WBS, and WBS dictionary
B. Cost baseline, quality baseline and schedule baseline
C. Configuration management plan and configuration identification document
D. Procurement statement of work and project scope statement - ✔✔-A. Scope statement, WBS, and
WBS dictionary
Which tool and technique is used in the processes Create WBS and Define activities?
A. Nominal group technique
B. Human resource assignment
C. Brainstorming
D. Decomposition - ✔✔-D. Decomposition
Which of the following statement(s) on whistleblowing is/are not true?
1. It is a term used to define an employee's decision to disclose information on unethical, immoral or
illegal actions at work to an authority figure.
2. An employee should always discuss the matter with people external to the company before following
the "chain of command" and discuss it with the immediate superior.
3. The consequences of whistleblowing are often extreme and might include being branded as an owner
of bad judgment, layoff, civil action and imprisonment.
4. Carefully performed whistleblowing can lead to the end of unethical business practices.
A. 1
B. 2
C. 2,3
D. 3,4 - ✔✔-B. 2
Which of the following statements is not true?
A. Attribute sampling is the process