WGU Project Management - C722, UNIT
7 TEST Questions and answers, graded
A+
_____________activities are activities that can be performed simultaneously because they involve
different resources.
Concurrent
Decrea
...
WGU Project Management - C722, UNIT
7 TEST Questions and answers, graded
A+
_____________activities are activities that can be performed simultaneously because they involve
different resources.
Concurrent
Decreasing ____________________ is possible by Inspecting tasks to see if they can be made shorter.
Critical Path
To provide a unique representation of each item on the network diagram, you can use which of the
following?
Work Breakdown Structures
Sequencing requirements
Budgets
Label nodes
Label Nodes
Between tasks you can insert _________________ to help shorten the overall duration.
Lead Time
The ___________________ used to complete project tasks can come from within or outside of the
organization hosting the project.
Resources
___________________________ depend on project deliverables, project constraints, milestones,
budgets, etc.
Task Relationships
The rows down the left margin in a ____________________ display key activities or stages of the project
in sequence.
GNATT Chart
What is the concept that suggests the more often a person completes a task, the better he or she
becomes at completing that task called?
Learning curve
Beta distribution
Work Breakdown Structure (WBS)
One-point estimate
Learning Curve
Which of the following is the logical relationship where the successor task cannot be completed until the
first task is completed?
Start-to-start relationships
Finish-to-finish relationship
Finish-to-start relationships
Start-to-finish relationships
Finish-to-finish relationship
You can reduce critical path by eliminating _____________ that may not be required to achieve the
desired end result.
Task
The goal of ___________________________ is to get the project delivered faster.
Schedule compression
As the project team develops the activity ____________________, they may divide activities or identify
additional activities that need to be added to the WBS.
duration estimates
A _______________________ is when you start assigning dates based on the earliest start date, adding
dates based on estimates for each task in the diagram.
forward pass
Which of the following is critical for creating accurate and realistic project plans and schedules?
Task relationships
Finish-to-start relationships
Successor activities
Predecessor activities
Task relationships
Working to________________________ is the first step to defining the critical path.
identify all the deliverables, activities, & tasks
Which of the following can be inserted between tasks to help shorten the overall duration?
Slack time
Lag time
Float time
Lead time
Lead Time
Lead time or _____________________________extends a link backward or forward so that the
successor task starts earlier or later than it otherwise would.
lag time
Which of the following approaches use basic statistics to account for uncertainty in activity duration
estimates?
Probabilistic duration estimation
Deterministic duration estimation
Scoring model
Project plan
Probabilistic duration estimation
______________________________ is the number of time periods required to finish work activities that
lead to the completion of the project deliverables.
Duration
To reduce critical path, which of the following should be reviewed to see if more are needed or the ones
currently in use need improvement