Running Head: COURSE PROJECT
1
Final Course Project
MGMT 404
Table of Contents
COURSE PROJECT
2
1. Scope Statement for Supersaver Energy Corps...............................................................2
2. Wo
...
Running Head: COURSE PROJECT
1
Final Course Project
MGMT 404
Table of Contents
COURSE PROJECT
2
1. Scope Statement for Supersaver Energy Corps...............................................................2
2. Work Breakdown Structure..........................................................................................3
3. Network Diagram..........................................................................................................4
4. Risk Management Plan....................................................................................................5
5. Resource Management Plan............................................................................................6
6. Communication Management Plan..................................................................................7
6.1 Communication Plan Approach.................................................................................8
6.2 Communication Constraints......................................................................................8
6.3 Communication Team Directory...............................................................................9
6.4 Flowchart for Communication...................................................................................9
Conclusion.........................................................................................................................10
Reflections of Lesson Learnt.............................................................................................11
References..........................................................................................................................12
COURSE PROJECT
3
1. Scope Statement for Supersaver Energy Corps
PROJECT OBJECTIVE
To make a household of area 2,600 sq.ft energy efficient within four months at the cost of
$120,000
DELIVERABLES
Create the household structure that would cover the house from external to increase
energy efficiency
Installation of ventilation system
Installation of effective temperature and lightning maintenance system
Energy efficient windows, doors and home appliances
MILESTONES
House Audit for energy leakage complete – January 10
Lay-out for energy efficient apparatus finalized – January 30
Loan approval obtained – February 10
Material procurement completed – February 28
Installation completed of energy efficient products – March 28
Testing complete – April 07
COURSE PROJECT
4
Household final handover to owner – April 10
TECHNICAL REQUIREMENTS
House meets the building codes prescribed by local authorities
Doors and windows pass heat and energy leakage stop test
Roof installation stops heat leakage
Electrical appliances and fixtures are energy efficient.
CUSTOMER REVIEW
Joe Smith
2. Work Breakdown Structure
WBS Task Name Duration Start Finish
1 Pilot Project 65 days Thu 1/10/13 Wed 4/10/13
1.1 House Audit 5 days Thu 1/10/13 Wed 1/16/13
1.1.1 Checking house for energy leak
points 1 day Thu 1/10/13 Thu 1/10/13
1.1.2 Ground power leakage checking 1 day Fri 1/11/13 Fri 1/11/13
1.1.3 Electricity bills of last 6 months
studied 1 day Mon 1/14/13 Mon 1/14/13
1.1.4 House audit complete 0 days Tue 1/15/13 Tue 1/15/13
1.2 Installation Preparation 24 days Wed 1/16/13 Mon 2/18/13
1.2.1 Lay-out for energy efficient
apparatus installation prepared 10 days Wed 1/16/13 Tue 1/29/13
1.2.2 Estimation of the number of
equipments to be installed 6 days Wed 1/30/13 Wed 2/6/13
1.2.3 Financial calculation of the
installation 4 days Thu 2/7/13 Tue 2/12/13
1.2.4 Loan approval obtained 3 days Wed 2/13/13 Fri 2/15/13
1.2.5 Installation preparation completed 0 days Mon 2/18/13 Mon 2/18/13
1.3 Equipment Procurement 10 days Mon 2/18/13 Fri 3/1/13
COURSE PROJECT
5
1.3.1 Finalizing material requirement 3 days Mon 2/18/13 Wed 2/20/13
1.3.2 Order placing for material 1 day Thu 2/21/13 Thu 2/21/13
1.3.3 Equipment to be delivered 6 days Fri 2/22/13 Fri 3/1/13
1.3.4 Equipment Procured 0 days Fri 3/1/13 Fri 3/1/13
1.4 Installation of Equipments 17 days Fri 3/1/13 Mon 3/25/13
1.4.1 Roof Top Installation 12 days Fri 3/1/13 Mon 3/18/13
1.4.2 Electrical fixtures installation 11 days Fri 3/1/13 Fri 3/15/13
1.4.3 Energy leakage preventors
installation 7 days Fri 3/15/13 Mon 3/25/13
1.4.4 Installation complete 0 days Mon 3/25/13 Mon 3/25/13
1.5 Final Audit 4 days Tue 3/26/13 Fri 3/29/13
1.5.1 Inspection of electric and structural
modification work 4 days Tue 3/26/13 Fri 3/29/13
1.6 Project completion 1 day Mon 4/1/13 Mon 4/1/13