Module 2 - Planning - Acquisition Strategy Development Part II Exam
Which of the following is NOT a required characteristic of a contractor's
quality management procesvc
1) Increment
...
Alabama State University
ACQ 202
Module 2 - Planning - Acquisition Strategy Development Part II Exam
Which of the following is NOT a required characteristic of a contractor's
quality management procesvc
1) Incremental funding policy applies to the _______ appropriation category
and states that ____________. [Given programming and budgeting documents, relate the
applicable funding policies to each of the five DoD appropriation categories of greatest interest to
acquisition programs.] [Remediation Accessed :N]
Research, Development, Test, and Evaluation (RDT&E); DoD is to fund
each fiscal year for the costs expected to be incurred that year.
Procurement; DoD is to fund each fiscal year for procurement costs to
be incurred that year.
Procurement; DoD is to fund the total costs incurred to deliver a given
quantity of useable end items.
RDT&E; DoD is to fund the total costs incurred to develop and test a
given quantity of useable end items.
2) With regard to exceptions to the full funding policy, _________ funds are
budgeted as a separate procurement line item from the related end item.
[Identify two exceptions to the full funding policy.]
Advance
Procurement
Multiyear
Procurement
Low Rate Initial Production
(LRIP)
Increment
al
3) When financial managers adjust for cost inflation in programming and
budgeting, they usually: [Identify the concept of escalation in submitting program and
budget documents.]
Prepare initial estimates in base-year (constant) dollars and escalate
costs into then-year (current) dollars
Refer to Federal Reserve Board guidelines on outlay rates and
income flows
Expect investment appropriations, such as Procurement and Research,
Development, Test, and Evaluation (RDTE), to have quick outlay rates
Revise their Program Objectives Memorandum (POM) submission based
on the Resource Management Decision (RMD) released by the Deputy
Secretary of Defense
4) A _______ is an aggregation of program elements that reflects a macrolevel force mission or support mission of DoD. [Relate the following building blocks
to the PPBE process: Future Years Defense Program (FYDP); Major Force Program (MFP); and
Program Element (PE).]
Major Force Program
(MFP)
Budge
t
Program Objectives Memorandum
(POM)
Future Years Defense Program
(FYDP)
5) The __________ presents the Component's (Service/Agencies) proposal for
service resources within specified constraints to satisfy the Defense
Planning Guidance (DPG). [Identify the key events in the programming phase, including the
preparation, review and decision process associated with the two primary documents of the phase:
Program Objectives Memorandum (POM) and Resource Management Decision (RMD).]
Program Objectives Memorandum
(POM)
Resource Management Decision
(RMD)
Budget Estimate Submission
(BES)
Budget Estimate Decision
(BED)
6) The Contracting Officer's responsibilities include all of the following
EXCEPT [Identify the complementary roles and responsibilities of the Contracting Officer and the
Program Manager in their partnership throughout the acquisition process.]
Managing performance of the contractor on a
daily basis
Preparing the request for
proposal
Conducting discussions with potential offerors in response to a
solicitation
Making a modification to an existing
contract
7) Market research and analysis shall also be conducted to identify and
evaluate possible ___________________ and ___________________ throughout
research and development. [Identify the role of various Integrated Product Team members
in conducting market research and developing the solicitation.]
dual use technologies / commercial
suppliers
product value / product
complexity
schedule delays / cost
increases
acquisition approaches / test
strategies
8) If the Government has funded the entire development of an item, the
Government is entitled to _______ rights. [Identify the policy and concepts involved in
the acquisition of data rights.]
Unlimite
d
Government
purpose
Limite
d
Restricte
d
9) Small business set-asides require the expectation that at least three
capable small disadvantaged businesses will submit offers. [Identify current
socioeconomic programs and determine their contractual consequences.]
True
Fals
e
10) To minimize software development risk, select a contractor who: [Identify
key laws and software acquisition management policies and practices that are required for the
acquisition of a DoD automated information system.]
Can demonstrate process maturity and domain
expertise
Complies with quality standard MILQ9858A
Is rated Level 1 on the Standard Capability Maturity Model Integration
Appraisal Method for Process Improvement (SCAMPI)
Relies on leading edge approaches and the latest state-of-the-art tools
for software development
11) Configuration management helps control software items and shared
information [Identify "best practices" that may be appropriate for the acquisition of softwareintensive systems.]
Fals
e
True
12) When selecting a software developer, which of the following should
contractors possess (Select all that apply)? [Identify key discriminators for selecting
the most capable software developer.] [Remediation Accessed :N]
Domain experience in developing comparable software
systems
Demonstrable mature software development capability and
processes
Maturity level
four
Successful past performance
record
13) Interoperability of command, control, communications, computers, and
intelligence (C4I) systems is confirmed through testing overseen by the
__________. [Identify the aspects of the Joint Capabilities Integration and Development System
(JCIDS) as it applies to acquisition of Information Technology (e.g., interoperability, architecture, reuse).]
Joint Interoperability Test Command
(JITC)
Under Secretary of Defense for Acquisition, Technology and Logistics
(USD, (AT&L))
Joint
Staff
Director, Developmental Test and Evaluation
(DDT&E)
14) In order to ensure that a contractor has an acceptable quality assurance
system in place, the Government can require that a contractor be ISO 9001
compliant. [Identify DoD policy regarding Basic Quality Systems and the role of ISO 9001.]
[Remediation Accessed :N]
Fals
e
True
15) The __________ phase translates planning decisions, OSD programming
guidance, and Congressional guidance into detailed allocations of timephased resource requirements. [Identify the basic flow of the financial management
process, to include cost analysis, the Planning, Programming, Budgeting and Execution (PPBE)
process, Congressional enactment, and program execution.]
Programmin
g
Plannin
g
Budgetin
g
Executio
n
16) Earned value management (EVM) reports are available to help the
program manager (PM) track the contractor's cost, schedule, and
performance against a Performance Measurement Baseline. [Recognize the
purpose and formats of the Integrated Program Management Report (IPMR).] [Remediation
Accessed :N]
True
Fals
e
17) Match the contract type with its best description. [Select appropriate contract
type based upon program risk.] [Remediation Accessed :N]
a
)
Cost Plus Incentive Fee
(CPIF)
b
)
Fixed Price Incentive
FPI)
c
)
Cost Plus Fixed Fee
(CPFF)
d
)
Cost Plus Award Fee
(CPAF)
Must have maximum/minimum fee
amounts
The fee amount doesn't
change
A ceiling price is
established
Requires subjective evaluation of the
contractor
b
Permits a subjective unilateral decision for amount of fee
Cost Plus Award Fee (CPAF)
contract type permits a subjective unilateral
decision for amount of fee to be awarded.
Allows for the adjustment of fee based on a share ratio and the cost overrun/underrun
Cost Plus Incentive Fee (CPIF)
contract type allows for the adjustment of fee
based on a share ratio.
Price is negotiated prior to contract award and will not change regardless of cost to
contractor
a
c
d
Firm Fixed Price (FFP)
contract type is when price is negotiated prior to contract
award and will not change regardless of cost to contractor.
Fee does not vary with actual costs
Cost Plus Fixed Fee (CPFF)
contract type is when fixed fee does not vary with
actual costs.
1) If your procurement budget request did not provide for buying a whole
number of useable end items, this would be a violation of which funding
policy? [Given programming and budgeting documents, relate the applicable funding policies
to each of the five DoD appropriation categories of greatest interest to acquisition programs.]
Full
Funding
Deficit
Funding
Incremental
Funding
Annual
Funding
2) What is the Government's basic purpose of using the Capability Maturity
Model Integration (CMMI) and the associated Standard CMMI Appraisal
Method for Process Improvement (SCAMPI) assessment process? [Identify key
discriminators for selecting the most capable software developer.]
To rate potential software developers on their ability to produce
software at a predicted cost and schedule using a four-level capability scale
and a five-level maturity scale.
Is used by contractors to show clients how they develop various types of
software.
It is a model of the specific software to be used in a
program.
Allows the contractor to rate their own software development processes
and experience on a multi-level scale. The Government would then look at
the contractor's self-assessment to produce defect-free software at a
predicted cost and schedule.
3) Which of the following is NOT a required characteristic of a contractor's
quality management process? [Identify DoD policy regarding Basic Quality Systems and
the role of ISO 9001.]
Appraise the product and inspect in
quality
Monitor and control product
variation
Implement a system for corrective
action
Establish a feedback
mechanism
4) When are all seven Integrated Program Management Report (IPMR)
formats required? [Recognize the purpose and formats of the Integrated Program
Management Report (IPMR).] [Remediation Accessed :N]
Cost and incentive contracts of $50 million or
more
All DoD
contracts
Cost and incentive contracts of $15 million
or less
Fixed price contracts of $15 million
or less
5) In a ________ type of contract, the contractor bears virtually all the
financial risk associated with procurement. [Select appropriate contract type based
upon program risk.] [Remediation Accessed :N]
Firm fixed
price
Cost plus award
fee
Cost plus incentive
fee
Sole source
1) Which of the following provides essential project data including
objective performance status, cost impact of known problems,
identification of emerging problems, possible sources of problems, and
schedule deviations from the contract plan? [Recognize the purpose and formats
of the Integrated Program Management Report (IPMR).] [Remediation Accessed :N]
Integrated Program Management Report
(IPMR)
Cost/Benefit
Analysis
Work Breakdown Structure
(WBS)
Integrated Master
Schedule (IMS)
Integrated Program Management Report (IPMR)
Used to obtain cost and schedule performance info
Provides essential project data
o Objective performance status in terms of cost and
schedule variances
o Cost impact of known problems
o Identification of emerging problems
o Possible sources of problems
o Schedule deviations from the contract plan
Updated estimates at completion
2) The type of contract decision is based upon which of the following?
[Select appropriate contract type based upon program risk.]
Allocation of cost risk between the
parties
Recommendation of the Configuration Control
Board
Amount of subcontracting
anticipated
Government's ability to obligate funds
1) Full funding policy applies to the _______ appropriation category and
states that ______. [Given programming and budgeting documents, relate the applicable
funding policies to each of the five DoD appropriation categories of greatest interest to acquisition
programs.]
Procurement and Military Construction; DoD is to fund the total costs
incurred to deliver a given quantity of useable end items.
Research, Development, Test, and Evaluation (RDT&E); DoD is to fund
the total costs incurred to develop and test a given quantity of useable end
items.
RDT&E; DoD is to fund the total costs to be incurred over a 12-
month period.
Procurement; DoD is to fund the total costs to be incurred over a 12-
month period.
2) Which of the following exceptions to the full funding policy would allow
the Government to budget for buying three years' worth of engines under
one contract in order to save money? [Identify two exceptions to the full funding
policy.]
Multiyear
Procurement
Advance
Procurement
Increment
al
Low Rate Initial Production
(LRIP)
3) Escalation allows us to make predictions about future costs based on:
[Identify the concept of escalation in submitting program and budget documents.]
Expected inflation and outlay
rates
Expected outlay rates and affordability
trade-offs
Expected inflation rates and affordability
analyses
Expected cost/performance trade-offs and affordability
analyses
4) The database that contains the force structure, personnel strength, and
financial resources of DoD is the: [Relate the following building blocks to the PPBE
process: Future Years Defense Program (FYDP); Major Force Program (MFP); and Program Element
(PE).] [Remediation Accessed :N]
Future Years Defense Program
(FYDP)
Planning, Programming, Budgeting and Execution System
(PPBE)
Resource Management Decision
(RMD)
Acquisition Program Baseline
(APB)
5) The Deputy Secretary of Defense documents his/her decisions about
Component (Service/Agencies) proposals for allocating resources in this
document, which later serves as the baseline for the service's Budget
Estimate Submission (BES) during the budgeting phase. This document is
known as the: [Identify the key events in the programming phase, including the preparation,
review and decision process associated with the two primary documents of the phase: Program
Objectives Memorandum (POM) and Resource Management Decision (RMD).]
Resource Management Decision
(RMD)
Program Objectives Memorandum
(POM)
Acquisition Program Baseline
(APB)
Future Years Defense Program
(FYDP)
6) Responsibility for awarding the contract and any modifications for
Government contracts rests with the _______. [Identify the complementary roles and
responsibilities of the Contracting Officer and the Program Manager in their partnership throughout
the acquisition process.]
Contracting
Officer
Program
Manager
Head of the Contracting
Agency
Defense Contract Audit
Agency
7) Market research and analysis shall also be conducted to identify and
evaluate possible ___________________ and ___________________ throughout
research and development. [Identify the role of various Integrated Product Team members
in conducting market research and developing the solicitation.]
dual use technologies / commercial
suppliers
product value / product
complexity
schedule delays / cost
increases
acquisition approaches / test
strategies
8) Which of the following describes DoD's policy on acquiring data rights?
[Identify the policy and concepts involved in the acquisition of data rights.]
Acquire only those data rights that are essential to meeting minimum
Government needs.
Acquire the maximum data rights possible within the scope of the
contract.
Acquire restricted data rights to protect the contractor's right to use,
modify, reproduce, release or disclose data to the general public.
Acquire unlimited data rights unless there is compelling justification to
do otherwise.
9) Contracts greater than $100,000 are reserved for small business. [Identify
current socioeconomic programs and determine their contractual consequences.]
Fals
e
True
10) To minimize software development risk, select a contractor who: [Identify
key laws and software acquisition management policies and practices that are required for the
acquisition of a DoD automated information system.]
Can demonstrate process maturity and domain
expertise
Complies with quality standard MILQ9858A
Is rated Level 1 on the Standard Capability Maturity Model Integration
Appraisal Method for Process Improvement (SCAMPI)
Relies on leading edge approaches and the latest state-of-the-art tools
for software development
11) Configuration management helps control software items and shared
information [Identify "best practices" that may be appropriate for the acquisition of softwareintensive systems.]
Fals
e
True
12) When selecting a software developer, which of the following should
contractors possess (Select all that apply)? [Identify key discriminators for selecting
the most capable software developer.]
Domain experience in developing comparable software
systems
Maturity level
four
Demonstrable mature software development capability and
processes
Successful past performance
record
13) Interoperability of command, control, communications, computers, and
intelligence (C4I) systems is confirmed through testing overseen by the
__________. [Identify the aspects of the Joint Capabilities Integration and Development System
(JCIDS) as it applies to acquisition of Information Technology (e.g., interoperability, architecture, reuse).]
Joint Interoperability Test Command
(JITC)
Under Secretary of Defense for Acquisition, Technology and Logistics
(USD, (AT&L))
Joint
Staff
Director, Developmental Test and Evaluation
(DDT&E)
14) Which of the following is NOT a required characteristic of a contractor's
quality management process? [Identify DoD policy regarding Basic Quality Systems and
the role of ISO 9001.]
Appraise the product and inspect in
quality
Monitor and control product
variation
Implement a system for corrective
action
Establish a feedback
mechanism
15) DoD services and agencies submit Program Objectives Memoranda
(POM) to OSD during what phase of the Planning, Programming, Budgeting,
and Execution (PPBE) process? [Identify the basic flow of the financial management
process, to include cost analysis, the Planning, Programming, Budgeting and Execution (PPBE)
process, Congressional enactment, and program execution.]
Programmin
g
Plannin
g
Budgetin
g
Executio
n
16) When are all seven Integrated Program Management Report (IPMR)
formats required? [Recognize the purpose and formats of the Integrated Program
Management Report (IPMR).]
Cost and incentive contracts of $50 million or
more
All DoD
contracts
Cost and incentive contracts of $15 million
or less
Fixed price contracts of $15 million
or less
17) In a ________ type of contract, the contractor bears virtually all the
financial risk associated with procurement. [Select appropriate contract type based
upon program risk.]
Firm fixed
price
Cost plus award
fee
Cost plus incentive
fee
Sole source
1) The primary unit of data in the Future Years Defense Program (FYDP)
and normally the smallest aggregation of resources controlled by the
office of the Secretary of Defense (OSD) is the __________. [Relate the following
building blocks to the PPBE process: Future Years Defense Program (FYDP); Major Force Program
(MFP); and Program Element (PE).]
Program
Element
Defense Appropriation
Item
Appropriation Line
Item
Work Breakdown Structure (WBS) Cost
Center