BUS 375 Project management Questions
and Answers Latest Updated 2022
Graded A+
Which of the following was an intangible benefit when a large corporation implemented a
company wellness plan to encourage and support he
...
BUS 375 Project management Questions
and Answers Latest Updated 2022
Graded A+
Which of the following was an intangible benefit when a large corporation implemented a
company wellness plan to encourage and support healthy employees' lifestyles?
A. Improved productivity
B. Reduced payments for insurance
C. Better decision-making capabilities
D. Reduced sick days taken ✔✔C
Elena is working on a project to create a new pet leash for her pet supply company.Which of the
following items is a deliverable, as opposed to a requirement?
A. A leash handle that can adjust the length to between four and eight feet
B. Luxury options in a range of leathers
C. Leashes available in red, brown, and navy blue
D. Prototypes to showcase at stakeholder meetings ✔✔D
Which of the following elements of a project is a project manager NOT responsible for
performing?
A. Gathering budget estimates
B. Overseeing the completion of deliverables
C. Completing a routine task
D. Coordinating the work of team members ✔✔C
Pedro had to keep the large trees from the nursery watered for three days when the landscape crew
rescheduled the date when they could help him plant.
Which of the triple constraints was impacted?
A. Cost
B. Time
C.Quality
D. Scope ✔✔B
If Olivia managed a project to create a new advertising campaign for a client and estimated the
price for purchasing three new licenses for graphic development software, which of the following
estimate types did she make?
A. Resource
B. Cost
C. Process
D. Time ✔✔B
Which of the following is the least likely reason for failure of Stacey's construction project if
several stakeholders involved in the project were unable to agree on the final design of the
deliverables?
A. Problems with unforeseeable circumstances
B. Problems with project participants
C. Problems with communications
D. Problems with the project process ✔✔A
One of Mary's employees, Adam, notified her that there is a good chance that one of the marketing
assistants included some copyrighted images in the ad campaign by mistake. Mary asked Adam to
have the marketing assistants immediately research the images used for copyright issues and create
new images to replace any problematic images.What is the probability of this risk occurring and
what is the impact on the project?
A. Low probability and high impact
B. Low probability and medium impact
C. High probability and low impact
D. Medium probability and low impact ✔✔C
Which of the following correctly describes the impact of a risk?
A. Impact is used to determine the methodology for a project.
B. Impact is the chance a risk will happen during a project.
C. Impact is derived from documenting assumptions about the project.
D. Impact is the effect a risk has on progress towards completion. ✔✔D
Which of the following describes a program?
A. Several projects that address the same opportun