ACQ 202 Module 4 Exam: Part II,
Questions with accurate answers,
Graded A+
What does it mean if a project has a Percent Spent of 90%, Percent Scheduled of 85% and Percent
Complete of 95%? - ☑☑The project is in good s
...
ACQ 202 Module 4 Exam: Part II,
Questions with accurate answers,
Graded A+
What does it mean if a project has a Percent Spent of 90%, Percent Scheduled of 85% and Percent
Complete of 95%? - ☑☑The project is in good shape and should early and within budget.
Your program is liable for payment on good and services received under a contract. Your payment,
based on a submitted invoice, for all or part of this obligation is a(n) __________. - ☑☑Expenditure
Which of the following is a valid reason for rebaselining the Performance Measurement Baseline (PMB)?
- ☑☑The plan for completing the remaining contract effort is no longer achievable.
Which of the following test items are determined by the Program Management office that is developing
a system? - ☑☑Critical Technical Parameters (CTPs).
With modeling and simulation, we model the system and then test the _________ to gather test
predictions. - ☑☑Model.
The following data is received from contractor: Budgeted Cost of Work Perform (BCWP) = $300 Cost
Performance Index (CPI) = 1.2 Budgeted Cost of Work Scheduled (BCWS) = $400 Schedule Performance
Index (SPI) = 0.75 Actual Cost of Work Performed (ACWP) = $250 Budget at Completion (BAC) = $1,000
Contractor's Latest Revised Estimate = $1,000 Equation for Estimate at Completion (EAC) Low = ACWP +
((BAC-BCWP)/(CPI)) Equation for EAC High = ACWP+((BAC-BCWP)/(CPI*SPI) Which of the following
represents the most reasonable EAC range for these data based on EVM? - ☑☑EAC Low: $833 - EAC
High: $1,028
What type of testing would be conducted to determine the effectiveness of the manufacturing process?
- ☑☑Production Qualification Testing (PQT).A(n) ________________ can be used for predicting program obligation performance and funding
requirements and identifying potential budget execution problems. - ☑☑Spending Plan
Which of the following statements is NOT true regarding the requirements and objectives associated
with an Integrated Baseline Review (IBR)? - ☑☑The initial IBR should be completed within six months of
contract award.
The specific information required for each milestone review can be found in _____. - ☑☑DoD
instruction 5000.02
Which of the following is FALSE?
a. Exit criteria are measurable and demonstrable.
b. Exit criteria must be successfully demonstrated before a program can proceed further.
c. Exit criteria are not specific to a particular phase of an acquisition program.
d. Exit criteria help mange and reduce risk. - ☑☑c. Exit criteria are not specific to a particular phase of
an acquisition program.
[Show More]