Nerc Test Questions and Answers Latest
2022
According to Nerc Standards, an emergency interchange transaction can be exempt from tagging
if it is less than_________________ ✔✔60 minutes
A BA or LSE that requests an E
...
Nerc Test Questions and Answers Latest
2022
According to Nerc Standards, an emergency interchange transaction can be exempt from tagging
if it is less than_________________ ✔✔60 minutes
A BA or LSE that requests an EEA 3 must complete and EEA 3 report and submit it to the RC
within how many days ✔✔2 business days
During restoration efforts load pick-ups should not exceed_____________ percentage of
synchronized generation capacity ✔✔5%
What are the two components that a system operator should be aware of for controlling
frequency during a system restoration if they are in an islanded situation ✔✔load and generation
What system was put in place to provide RC's with a mechanism to handle energy deficiencies?
✔✔Energy Emergency Alerts
If due to a reliability event, an interchange transaction must be modified, how long does the Sink
Balancing Authority have to modify the tag? ✔✔withing 60 minutes of the start of modification
What is an example of a disturbance that has caused you system to become islanded?
✔✔Frequency Fluctuations
What is an instance is which you use manual load shedding? ✔✔Continuous decline in
frequency
What actions should be implemented during a EEA 2 ✔✔Schedule emergency assistance, recall
all non-firm exports, start all available generation
What would be an appropriate situation for a system operator to shed load? ✔✔Transmission
facility is overloaded, voltages are rapidly decaying, and no other situations are available
If an RC issues you a directive to implement when should it be implemented? ✔✔Without delay,
within 30 minutes
Each Operating Authority should periodically practice________________ ✔✔Simulated
emergencies
If a Transmission Operator has an anticipated emergency condition, it shall
inform_________________ ✔✔Its RC and any other potentially affected Transmission
Operators
How often shall the Transmission Operator and BA review and update each emergency
plan___________ ✔✔Annually
According to Nerc Standards, emergency plans must include interim provisions if it is expected
to take more than how many minutes to implement the contingency plan for loss of primary
control facility ✔✔60
Which EEA is used to announce the change in transmission service priority? ✔✔EEA 2
Who is the only entity that can declare an EEA? ✔✔Reliability Coordinator
Who must a system operator receive approval from to manually shed load? ✔✔No one
Automatic load shedding schemes should consider the following 3 things........ ✔✔frequency, the
rate of frequency decay, the rate of voltage decay
Blackstart capabilities should be verified by______________ ✔✔periodic testing
Synchroscopes should be calibrated in_____________ ✔✔degrees
What type of relay is relay 87? ✔✔Differential relay
If Ace is -50 before a disturbance it must return to____________ ✔✔-50
The disturbance recovery period is__________ minutes after the start of of a reportable
disturbance. ✔✔15
What are the 3 types of AGC? and what is AGC? ✔✔Constant Frequency, Constant Interchange,
Tie-line Bias
What type of relay is relay 21? ✔✔Dista