Module 6 Exam (contains 9 questions)
• Here is your test result.The dots represent the choices you have made.
• The highlighted questions are the questions you have missed.
• Remediation Accessed shows whether you acc
...
Module 6 Exam (contains 9 questions)
• Here is your test result.The dots represent the choices you have made.
• The highlighted questions are the questions you have missed.
• Remediation Accessed shows whether you accessed those links.'N' represents links not
visited and 'Y' represents visited links.
1.) Which of the following is a problem that could likely be minimized through good deployment planning?
Insufficient modeling and simulation
Inadequate testing
Inadequate training
Interoperability needs
2.) Decreased operational availability (Ao), increased costs, and bloated inventories may result from ______________.
Supportability analyses
Footprint reduction
Resolved supportability issues
Unresolved supportability issues
3.) Which core ethical value are you violating if you reject an opposing point of view during a disagreement and call it a shortsighted,
uninformed way to look at the situation?
Civic virtue and citizenship
Trustworthiness
Responsibility
Respect
4.) What method is generally preferred to resolve contract disputes because it saves time, money, and preserves relationships between the
parties?
Litigation (settling the dispute in court)
Termination of the contract for convenience
Termination of the contract for default
Alternative dispute resolution
5.) Which of the following is sufficient justification to terminate a contract for convenience?
The Government no longer needs the goods or services in the contract.
The contractor fails to deliver their product on time.
The contractor endangers the timely delivery of a commercial item.
The contractor fails to comply with the terms specified under the contract.
6.) What is the purpose of fielding/deployment planning?
To provide for a smooth introduction of the system to the user.
To ensure all functional disciplines will be integrated into system design.
To ensure all necessary funding will be programmed to support the system throughout its useful life.
To ensure the system will meet critical technical performance parameters established in the Capability Production Document.
7.) The contractor is solely responsible for providing post-production support.
True
False
8.) Match the leadership styles with the best response:
Coordinates group effort
Directs individual workers
Expands group capabilities
9.) Once unexpended Research, Development, Test and Evaluation (RDT&E) funds have expired, they can be used for
_____________________.
Participative Leadership
Supervisory Leadership
Team Leadership
New obligations
New Procurement obligations only
New RDT&E obligations only
Payments or adjustments to the original obligations
Module 6 Exam
• Here is your test result.The dots represent the choices you have made.
• The highlighted questions are the questions you have missed.
• Remediation Accessed shows whether you accessed those links.'N' represents links
not visited and 'Y' represents visited links.
Back to Status page
contains 9 Questions
1) Taking a contractual dispute to court should be the first step in
attempting to resolve controversy between the disputing parties. [17d.
Identify the process for resolving disputes between parties of a contract.]
True
Fals
e
2) When Congress does not appropriate sufficient funds to cover the cost of
work to be performed under a contract, the Government may: [17e. Contrast the
difference between termination for convenience, termination for default, and termination for cause.]
Terminate the contract for
convenience
Terminate the contract for
default
Terminate the contract for
cause
All of the answers are
correct
3) Which of the following tends to be a typical recurring deployment problem
when effective deployment planning is NOT accomplished? [34a. Identify life cycle
product support activities and requirements that deal with fielding/deployment (e.g., planning,
coordination, organizing deployment teams, materiel release).]
Continuing system
modifications
Inadequate operational
testing
Contractor cost and schedule
variance
Poor
design
4) Who is responsible for planning post-production logistics support? [34b.
Identify life cycle product support activities and requirements associated with post-production support
(e.g., planning, adequate sources of supply, spares modernization and sustaining system readiness).]
Program
Manager
Contracto
r
User
Command
Component Logistics
Command
5) Post-production support is essential ___________. [35a. Identify system
supportability issues in planning and executing a defense acquisition program.]
To ensure the system will continue to be sustained after production lines
have closed.
To ensure reducibility of the
system.
To establish how system technical data will be acquired prior to initial
system deployment.
To ensure sufficient funding is available for any problems that
may occur.
6) The primary difference between the supervisory leader and the
participative leader is the participative leader ____________. [5c. Discover how
different leadership styles impact the effectiveness of an Integrated Product Team (IPT).]
Gets inputs for
decisions
Directs
people
Trains
individuals
None of the answers are
correct
7) Unexpended funds that have expired may be used to pay for new
obligations. [Given a funding shortfall, apply rules governing the use of expired funds to resolve
the problem.]
True
Fals
e
8) Unresolved supportability issues may result in each of the following,
except which one? [Determine the impacts to a given acquisition program if supportability
issues are not resolved.]
Increased operational availability
(Ao)
Decreased
reliability
Increased logistics
footprint
Increased
cost
9) Which core ethical value are you violating if you hide information from
your team about an impending budget cut? [Identify core ethical values critical to
decision making in the acquisition environment.]
Trustworthine
ss
Respec
t
Justice and
fairness
Carin
g
[Show More]