Contains 4 Questions (Attempt=2/3)
Module 4 Exam
1) Consider the differences between the Program Evaluation and Review Technique
(PERT) and Arrow Diagram Method (ADM) network schedules. Which of the following is
a tr
...
Contains 4 Questions (Attempt=2/3)
Module 4 Exam
1) Consider the differences between the Program Evaluation and Review Technique
(PERT) and Arrow Diagram Method (ADM) network schedules. Which of the following is
a true statement? 4.4 pg. 59 of 73
PERT uses an "Activity-on-Node" method while ADM uses an "Activity-on-Arrow"
method.
PERT uses three time estimates while ADM uses only one time estimate.
PERT uses one time estimate while ADM uses three time estimates.
PERT uses an "Activity-on-Arrow" method while ADM uses an "Activity-on-Node"
method.
2) Which schedule time constraint solution is best used when the project has some
flexibility in the end date and a longer time to complete the project can be
accommodated?
Shortening task durations for tasks on the critical path
Accepting a longer length of time for the project
Conducting some tasks concurrently
"Crashing" the schedule
3) How does the Integrated Master Schedule (IMS) relate to the Integrated Master Plan
(IMP)? 4.2 pg. 23 of 28 (VERBATIM)
The IMS is traceable to the IMP and is a time-based extension of the tasks identified in
the IMP.
The IMS identifies the time frames to be used in the development of the IMP.
The IMP is a high-level document that identifies the tasks to be accomplished while the
IMS breaks down the tasks into actionable items.
1
10162551 1
10162565 1
10162518 1
The IMS provides a more detailed description of the tasks identified in the IMP.
4) Which of the following is the correct order of the process for building a Precedence
Diagramming Method (PDM) schedule? 4.9 pg. 46 of 50
Estimate task durations, determine resource requirements, identify the tasks, sequence the
tasks, construct schedules, monitor and control schedules
Identify the tasks, sequence the tasks, determine resource requirements, estimate task
durations, construct schedules, monitor and control schedules
Identify the tasks, sequence the tasks, estimate task durations, determine resource
requirements, monitor and control schedules, construct schedules
Determine resource requirements, identify the tasks, sequence the tasks, estimate task
durations, monitor and control schedules, construct schedules
10162578 1
[Show More]