FORMULATION EXAM: Introduction to Budgeting Exam
1) In late December, the Components revise their final budgets and begin preparing
supporting documentation to incorporate the effects of all Resource Management
Decisi
...
FORMULATION EXAM: Introduction to Budgeting Exam
1) In late December, the Components revise their final budgets and begin preparing
supporting documentation to incorporate the effects of all Resource Management
Decisions (RMDs) for inclusion in the President's Budget.
True
False
2) Advanced Procurement funding information shown on the P-5 budget exhibit should be
consistent with that shown on the _________ budget exhibit.
P-10 (Advanced Procurement Requirements Analysis)
P-3a (Individual Modification)
P-1 (Procurement Program)
P-21 (Production Schedule)
3) Which one of the following best describes the purpose of the P-3a budget exhibit?
Provide budget justification for a particular Procurement line item
Provide detailed information regarding monthly production of ACAT I program items
Summarize the funding requirements for a particular Procurement appropriation account
Provide budget justification for a particular Procurement-funded weapon system modification
program
4) The President's Budget that is submitted to Congress on the first Monday in February
is for fiscal year that will begin _____.
The current fiscal year
Two years out
In eight months (i.e., 1 October)
Four years out
5) Which one of the following best describes the conditions under which a P-1 budget
exhibit is required to be submitted?
When the program element funding is $1 million or more in any budget year covered by the budget
request
When any funding is requested under a particular Procurement appropriation
When the line item funding is $5 million or more in any of the budget years covered by the budget
request
When it covers a weapon system modification program whose costs exceed $5 million in any year
covered by the budget request
6) Which one of the following best describes the conditions under which an R-4 budget
exhibit is required to be submitted?
When a major program milestone is scheduled to occur during any budget year covered by the budget
request
When any funding is requested for a project that is part of a program element in RDT&E budget
activities 1, 2, or 3
When a project is part of a program element in RDT&E budget activities 4, 5, or 7 and requires $5
million or more of funding in any budget year covered by the budget request
When a project is part of a program element in RDT&E budget activities 4, 5, or 7 and requires $1
million or more of funding in any budget year covered by the budget request
7) What activities would a program office using the Resource Allocation Process shown be
involved in during the July 2017 timeframe when allocating its RDT&E funds?
(MAGE DESCRIPTION: This chart is associated with the text on the main page. It illustrates
the overlap in the management of program resources.
As shown here, in July 2017 (FY17), a program office using only Procurement funds might
be:
- Managing the execution of its FY15, FY16 and FY17 funds;
- Tracking the Congressional enactment of its FY18 budget request;
- Preparing its portion of the Integrated Program and Budget Review documentation for its
FY19-23 funding requirements.)
Managing the execution of its RDT&E funds for FY 16 (first year of availability).
Preparing its portion of the Program and Budget Review documentation for its FY20-24 POM
submission.
Managing the execution of its RDT&E funds for FY 17 (second year of availability).
Managing the execution of its RDT&E funds for FY 17 (first year of availability).
8) Use the Table of Raw and Weighted Indexes and the Windows Calculator under
Accessories to help select the correct answer.
An item to be financed by Appropriation A cost $100M in constant FY13 dollars.
The program will not be contracting for the item until FY18.
Fiscal Year Raw Index
(FY13 Base year)
Weighted Index
(FY13 Base Year)
2012 0.09833 1.0066
2013 1.0000 1.0223
2014 1.0130 1.0395
2015 1.0302 1.0585
2016 1.0488 1.0785
2017 1.0687 1.0990
2018 1.0890 1.1198
2019 1.1097 1.1411
What is the amount that should be budgeted for this item in FY18?
111.9800M
102.2300M
100.6600M
114.1100M
9) Which one of the following is displayed in the P-5a budget exhibit?
Production lead time for each end item
Initial Spares funding for 1 or 2 budget years and the two years preceding the first budget year
Contract award information for each applicable Work Breakdown Structure element
Narrative justification for a line item's budget request
10) When is the President's Budget produced in the Budgeting Phase of PPBE cycle?
February
August-December
Spring of each calendar year
July/August
11) Which of the following information is displayed in the P-10 budget exhibit?
Production and contract forecasts related to each "Advance Procurement" item found on the P-1
Funding information only for the budget year (1 year)
8-year funding details on each "ACAT I" program items listed on the P-21.
Forecast details on all the procurement line items that are on the P-1.
12) Which of the following statements is better for the Impact Statement?
A. Will lose one man-year of contractor support needed to produce ICBM modernization
kits.
B. Operational test (OT) of the ICBM modernization program will be delayed 8 months
because of delays in producing the ICBM modernization kits; delay in OT will delay
fielding of the system for at least one year, delaying the combat readiness of the modified
ICBM to the warfighter
A
Neither statement is appropriate for Impact Statements
They are both equal as Impact Statements
B
13) DoD funding policies are the ground rules, derived from Congressional direction,
concerning the __________ for various budget requests for various appropriations.
Reclama
Congressional language
Programming
Amount & timing
14) All of the following are considered a principle player of the Budgeting phase
EXCEPT:
Service/Component PPBE Action Officers (PEM, RO, DASC)
Component Staffs
Under Secretary of Defense (Policy)
Deputy Secretary of Defense
15) Which one of the following best describes the conditions under which an R-2a budget
exhibit is required to be submitted?
When an RDT&E program element consists of more than one project
When the program element funding is $1 million or more in any budget year covered by the budget
request
When funding is requested for a particular RDT&E program element
When the program element is part of RDT&E budget activities 4, 5, or 7
16) Which one of the following best describes the conditions under which an R-1 budget
exhibit is required to be submitted?
When it covers a weapon system modification program whose costs exceed $5 million in any year
covered by the budget request
When any funding is requested under a particular RDT&E appropriation
When the program element is part of RDT&E budget activities 4, 5, or 7
When the program element funding is $1 million or more in any budget year covered by the budget
request
17) Which one of the following is NOT normally involved in reviewing the information in
budget exhibits?
OSD Comptroller Staff
Component Staff
USD Policy Staff
Program Office
18) Which one of the following best describes the conditions under which an R-3 budget
exhibit is required to be submitted?
When the program element is part of RDT&E budget activities 4, 5, or 7
When it covers a weapon system modification program whose costs exceed $5 million in any year
covered by the budget request
When any funding is requested under a particular RDT&E appropriation
When the program element is part of RDT&E budget activities 1, 2, 3, or 6
19) Which of the following is a significant issue of concern for the OSD Budget Analyst
during review of budget justification documentation?
System quality
Program pricing
Program milestones
System support
20) Which of the following products of the Budgeting Phase includes the component's
final budget revisions and supporting documentation that incorporates the effects of all
RMDs?
Resource Management Decisions (RMD)
Budget Review w/OSD-C and OMB
President's Budget (PB)
Major Budget Issues (MBI)
21) What is the purpose of the Financial Management Regulation, 7000.14-R?
Authorizes the type and amounts of appropriations to support defense programs, sets military
personnel end strength levels, and establishes policies pertaining to specific programs and to the defense
establishment.
Provides authorization for major weapon system acquisition programs and military construction
projects and establishes procurement quantity ceilings for major weapon systems.
Direct statutory and regulatory financial management requirements, systems, and functions for all
appropriated and non-appropriated, working capital, revolving, and trust fund activities.
22) The R-1 budget exhibit summarizes the budget requirements for a specific RDT&E
appropriation account. Each R-1 budget exhibit line item (program element) is supported
by an _____.
R-3 (Program Element/Project Cost Analysis)
R-4 (Schedule Profile)
R-4a (RDT&E Schedule Detail)
R-2 (Budget Item Justification)
23) Which of the following is a reason that acquisition programs may lose funding during
the PPBE process?
The applicable appropriation is unclear
No system quality factors
Missing system support concept
Excessive risk
24) Perform a conversion to compare costs between the two programs below, to find out
which is the more expensive program. (Use the Windows Calculator under Accessories to
help select the correct answer.)
Program A estimated cost in constant FY13 dollars: $14M
Program B estimated cost in constant FY18 dollars: $20M
FY 2013 Raw Index (Base Year 2013): 1.0000
FY 2018 Raw Index (Base Year 2013): 1.0890
Which program is more expensive?
Fiscal Year Raw Index
(FY13 Base year)
2012 0.9833
2013 1.0000
2014 1.0130
2015 1.0302
2016 1.0488
2017 1.0687
2018 1.0890
2019 1.1097
Program A
Program B
25) What entity is charged with the task of providing answers to "advanced questions?"
Members of Congress
The SECDEF
OSD staff
Components
26) Which of the following information is displayed in the P-5 budget exhibit? Lesson 5.8
Production lead time for each end item
Unit costs for flyaway cost elements
Contract award information for each applicable Work Breakdown Structure element
Detailed Work Breakdown Structure elements and cost on advance procurement and modifications
27) Which of the following are one of the primary inputs of the Budgeting Phase?
Program Office Estimate (POE)
Budget Review USD(C) Leads
Chairman's Program Recommendations (CPR)
Will Cost
28) All of the following information is displayed in the P-40 budget exhibit, EXCEPT:
Funding information for the 2 years prior to the first budget year and 4 out-years following the last
budget year
Specific quantities of end items funded each year
Funding information for 1 or 2 budget years
Status for each individual modification
29) Which of the following information is displayed in the P-21 budget exhibit?
Contract award information for each applicable Work Breakdown Structure element
Minimum, economical, and maximum production rates
Contract history (prior year or last procurement, current year, budget years 1 and 2)
Listing of all items that will be purchased with advance procurement funds
30) The Annual Funding Policy applies to which of the following categories of
appropriations?
Procurement
Military Construction
Research, Development, Test & Evaluation
Operations & Maintenance
[Show More]